9
|
Good morning, Our question regarding selection criterion T3 and more specifically, the required expertise [...]
|
1 - 5 years of professional experience is requested for each individual expert. 2 - The minimum requirement [...]
|
22/01/2020
|
|
8
|
The criterion specifies that the team should at minimum include three members from the specified list [...]
|
The team must be composed of at least 3 people, and the team as a whole needs to meet the sub-criteria [...]
|
21/01/2020
|
|
7
|
Is there a form for the technical offer?
|
No, there is no specific form for the technical offer.
|
21/01/2020
|
|
6
|
With reference to the note on "tenderers established in the United Kingdom" -does rejection from the [...]
|
The rules on access to the market do not apply to subcontractors. Thus subcontractors established in [...]
|
20/01/2020
|
|
5
|
We have a wide experience on researches, ordered by the Spanish government, related to musicians and [...]
|
The corrigendum of the Tender Specifications will be published as follows: At least 2 experts on health-related [...]
|
20/01/2020
|
|
4
|
1 - the criterion T3 (page 24) indicates that the project manager needs “at least 5 years´ experience [...]
|
1 - No, this would be a national level project. 2 - Publications need to be in English
|
10/01/2020
|
|
3
|
Could you confirm which of the two options is correct with regard to selection criteria T1 and T2? a) [...]
|
Each of these criteria applies to the tenderer as a whole, i.e. the combined capacities of all involved [...]
|
10/01/2020
|
|
2
|
Could you specify what "local authorities" under T3, the requirements for the project manager (P.24) [...]
|
Local authorities mean self-governing authorities working on the administrative level of cities, communes [...]
|
02/12/2019
|
|
1
|
Dear sir, madam, We are confused by the Annexes 5.1 and 5.2. The draft text for Annex 5.2 mentions only [...]
|
Yes, a tenderer may rely on subcontractors to fulfil the selection criteria, as described under Section [...]
|
29/11/2019
|
|