212
Do you agree that CRs above a certain size are subject to analysis and mutual approval, e.g. 20MDs
The EMA has approval processes in place for change request approval based on man days. The supplier will [...]
07/05/2020
Răspuns primit
211
When calculating the resolution time, do we take into account that the tests are completed by the AMS [...]
Any items deployed into the Production system would be subject to a change request, planned and contained [...]
07/05/2020
Răspuns primit
210
Can you please confirm that you have Standard procedures detailed and that they contain information such [...]
For technical activities the SAP Basis consultant would apply standard SAP processes, liaising with the [...]
07/05/2020
Răspuns primit
209
Shall we assume that there is a Bug guarantee - everything is an error as long as it is not our CR. We [...]
Any issue type that involves an element of a third-party error allows for suspension during the resolution [...]
07/05/2020
Răspuns primit
208
Answer of Criterion 3 must not exceed 5 pages. Nevertheless, considering the amount of topics to tackle [...]
We appreciate the willingness to provide the most complete and comprehensive answer. And it is true that [...]
07/05/2020
Răspuns primit
207
Considering the current COVID outbreak situation, we would like EMA to reconsider the submission of award [...]
A single document should be provided with all answers to the award questionnaire for each lot individually [...]
07/05/2020
Răspuns primit
206
Could EMA clarify what they would like to see in the answer to criteria 3 Lot 1? Does EMA expect to see [...]
EMA is expecting to evaluate the ability and proficiency of the tender in delivering Office 365 solutions [...]
07/05/2020
Răspuns primit
205
Does EMA expect to see any estimations/detailed pricing for the LOT1 – Criteria’s scope?
No pricing information need to be provided as part of the answer. Detailed information are expected, [...]
07/05/2020
Răspuns primit
204
Assuming scope of work in SharePoint Online is migration of Documentum data to SharePoint Online with [...]
This is the correct assumption.
07/05/2020
Răspuns primit
203
Assuming Documentum migration on SharePoint Online will be a separate scope from D365 implementation, [...]
This is the correct assumption. Migration from Documentum to Sharepoint online is separate from Dynamics [...]
07/05/2020