80
|
Article II.6.3 states that the contractor is liable for all damage. In our opinion however, liability [...]
|
Please see the response to question 79.
|
12/08/2019
|
|
81
|
On the one hand, contractor believes that there must be a possibility for liability on the part of the [...]
|
Please note Article II.6.1. draft framework contract refers to contracting authority not being liable [...]
|
12/08/2019
|
|
67
|
The penalty clause in Annex XVI states that the fine is immediately due and payable when the service [...]
|
Please see answer to question 34. A penalty is applied if the contractor fails to comply with the KPI [...]
|
07/08/2019
|
|
82
|
Article II.15 contains a formula for the calculation of the delay damage that the contractor owes if [...]
|
Please note EMA is obliged to include liquidated damages clause (i.e. provision II.15) in the award contract [...]
|
12/08/2019
|
|
83
|
A definition of 'force majeure' is included in article II.1 of the FWC. It states that strikes are in [...]
|
Please note the Agency is aware and takes into consideration applicable limitations stemming from Dutch [...]
|
12/08/2019
|
|
84
|
Article II.16.1 of the FWC states that the contracting authority is entitled to reduce or reclaim the [...]
|
Please note that in case of lack of performance or underperformance by the contractor (Article II.16.1 [...]
|
12/08/2019
|
|
85
|
Is it an option / is there any room to place a 'molok' (underground container) to limit the transportations [...]
|
No, there is no space available for a ‘molok’ type of container.
|
13/08/2019
|
|
70
|
Tenderers can insert suggested machines “compactors/containers/pressers” in Annex II Costing sheet under [...]
|
A new Costing sheet (v.3) has been published for tenderers where relevant cells have been unblocked. [...]
|
09/08/2019
|
|
86
|
Definition of sanitary unit: A sanitary unit is a room in your building that contains several toilets [...]
|
Please see the new annex ‘XIX’ (Specifications of sanitary units) which has been published with additional [...]
|
13/08/2019
|
|
87
|
The start date of the contract is foreseen to be 01 December 2019. Can you confirm that this is the date [...]
|
This understanding is correct: the start of the contact will be the start date of the contract implementation [...]
|
13/08/2019
|
|
71
|
According the demands of WELL and BREEAM, we would like to offer products which meets these demands. [...]
|
Tenderers must submit quotes according to the specifications to ensure fair comparison between tenders [...]
|
09/08/2019
|
|
88
|
There are no bins asked for the hand towels. In our opinion it’s necessary to add bins especially for [...]
|
Please see the answer to question 86. Bins are provided in the building.
|
13/08/2019
|
|
68
|
In question 2 you have given us indicative measures per floor. In this list, the measures of floor 3 [...]
|
Please see below rectification: Floor 4 to 18: standard offices floors: surface 1,350 – 1,435 m2 + bathrooms [...]
|
08/08/2019
|
|
72
|
Is there an obligation to take over members of the current cleaning staff?
|
Please be informed that the EMA is currently making use of a fully serviced temporary accommodation, [...]
|
09/08/2019
|
|
73
|
You indicate at the sanitary consumables that the toilet paper must have a length of 240 cm. Do we assume [...]
|
Please refer to question 22.
|
09/08/2019
|
|
74
|
We do not find any soap at the sanitary consumables in the costing sheet. Can you indicate why you are [...]
|
Hand soap has been added to the Costing sheet in sheet 1 (Cleaning services) in section 2: Consumables [...]
|
09/08/2019
|
|
89
|
Are the costs of supplying the vending machines for the tenderer? If so, what is the expected consumption [...]
|
As per annex II (Costing sheet) the tenderers must include in their quote the cost of provision and maintenance [...]
|
13/08/2019
|
|
75
|
Does the tenderer correctly understand that in part two a price must be entered for the consumbles requested [...]
|
Yes, the understanding is correct; the quotes for consumables should not include dispensers.
|
09/08/2019
|
|
76
|
Why do you ask for a different frequency of replacing the bins on the (MIVA) invalid tiolet?
|
The frequency of replacing the bins is based on the Agency’s previous experience. Frequency could be [...]
|
09/08/2019
|
|
90
|
In your answer on question 43 you state that the contract start date is foreseen to be 01 December ‘19 [...]
|
Please see the response to question 87.
|
13/08/2019
|
|
92
|
What is the width of the access road to expedition/’Milieustraat’? Can you confirm that waste collector [...]
|
The size of the truck that can enter the expedition road and area is limited to the size as specified [...]
|
19/08/2019
|
|
98
|
In this section you ask for 47 Enzyme and urinal sleeves for each urinal. Can you specify this product [...]
|
The urinals are not waterless. The Agency does not prescribe the type of product to be used; this will [...]
|
22/08/2019
|
|
99
|
In this section you ask for '25 x Sharp bins for each disabled toilet'. Are you sure you want sharpbins [...]
|
The requests for 25 sharp bins for each disabled toilet is based on what was in use in the Agency’s previous [...]
|
22/08/2019
|
|
100
|
In this section you ask for '1 small clinical waste bin and 1 sharp bin in the first aid room'. These [...]
|
The Agency cannot remove the supply and servicing of clinical waste bins and sharp bins from the requirements [...]
|
22/08/2019
|
|
97
|
Hand soap has been added to the Costing sheet in sheet 1 (Cleaning services) in section 2: Consumables [...]
|
A new costing sheet (v.4) has been published in which the formula is corrected. Tenderers must use this [...]
|
21/08/2019
|
|