25
In order to better devise our approach to carrying out the takeover of the complete set of existing IT [...]
The reply provided by the contracting authority on Oct 25, 2017 4:50:31 PM to the question with subject [...]
26/10/2017
Zodpovedaná
24
Could you please specify the difference between the - finale progress report (as described in 1.20 of [...]
The Tender specifications in point 1.20 refer to "final progress reports": these are the reports documenting [...]
18/10/2017
Zodpovedaná
23
Is it OK to fill in 0 Euro for the offer, as the system requires to fill something in, whereas the financial [...]
Yes, you may fill in 0 in eSubmission third step, as the relevant financial offer to this call for tenders [...]
17/10/2017
Zodpovedaná
22
As far as we’ve understood it is not clear how the overall budget for the ESAA project is to be distributed [...]
As explained in the Tender Specifications, section 1.17, all services needed under this FWC shall be [...]
16/10/2017
Zodpovedaná
21
Taking into consideration the duration of different events clarified earlier and the table provided in [...]
As explained in the introduction to Annexes 5a and 5b, tenderers are expected to describe the approach [...]
16/10/2017
Zodpovedaná
20
We are no WTO experts but want to clarify the possibility of participation. Given a consortium, in which [...]
According to the Financial Regulation (Regulation 966/2012), participation in procurement procedures [...]
09/10/2017
Zodpovedaná
19
Under the provision of secretarial services, in connection with the task of "Accepting of new members [...]
Reference is made to task 4 of the tender specifications. Membership of the Erasmus Mundus Student and [...]
06/10/2017
Zodpovedaná
18
According to the technical specification and the Annex 4: Price Quote form IT experts and Survey Experts [...]
According to the technical specification and the Annex 4: Price Quote form, with regards to line n° 4 [...]
04/10/2017
Zodpovedaná
17
if expenses -like hosting the databases/websites- etc. are not regarded as reimbursable expenses in the [...]
As we have stated in our published answer to previous Questions on reimbursables and managing costs, [...]
04/10/2017
Zodpovedaná
16
Are all planned internal meetings as described in task 2 foreseen to be 1-day meetings?
Reference is made to the Tender Specifications, task 2. Please note that the duration of internal meetings [...]
04/10/2017
Zodpovedaná