10
|
Should the administrative documents, i.e. power of attorney, turnover, legal entity form, etc be delivered [...]
|
The administrative documents have to be submitted, in hard copy along with all tender documents, in one [...]
|
21/06/2016
|
|
9
|
The Draft contract includes two articles that could generate doubts about preexisting elements: I.10.2 [...]
|
The two paragraphs of Article I.10.2 are alternative. The first paragraph will be retained for the signed [...]
|
21/06/2016
|
|
8
|
Page 17 mentions: "The tenderers will provide evidence that he delivered at least 1 project related to [...]
|
The tenderers will provide evidence that he delivered at least 1 project related to the fields mentioned [...]
|
09/06/2016
|
|
7
|
Task A1.1 states that the action plan will be submitted to the Flightpath Core Team. Is that also true [...]
|
No, it is not requested to submit to the Biofuel Flightpath Core Team the draft version of the plan that [...]
|
09/06/2016
|
|
6
|
Task A1.7 requests the proposal of a new renewable fuel "Flightpath" at M12. Could you precise what is [...]
|
Yes, we are referring to the process initiated in 2011 under the name 'Advanced Biofuel Flightpath'. [...]
|
03/06/2016
|
|
5
|
The payment plan in the Draft Contract is very hard on any supplier, and especially disadvantages SMEs [...]
|
Please be informed that the payment conditions cannot be changed.
|
27/05/2016
|
|
4
|
The Tender Specifications, on page 17, states that "relevant services" must be from past THREE years [...]
|
The project references indicated in the technical specification can be selected from projects conducted [...]
|
27/05/2016
|
|
3
|
Section 4.2.2. (Regulatory capacity) of the Tender Specifications states that "Tenderers must prove that [...]
|
Please be informed that regulations for performing certain professions vary in different countries. If [...]
|
27/05/2016
|
|
2
|
The Invitation letter states that ONLY the lead partner (in case of a joint tender) should complete and [...]
|
There is no discrepancy between the invitation to tender and Annex I to the tender specifications. In [...]
|
27/05/2016
|
|
1
|
Referring to the requirement at the bottom of p17 of the ToR, are you willing to reduce the limit with [...]
|
Please be informed that the threshold will not be changed as it represents less than 25% of the designated [...]
|
27/05/2016
|
|