Tenderers are requested to note that the closing date for submission of tenders has been extended to 03/07/2020 at 12:00 and the opening of tenders will now take place on 06/07/2020 at 14:00.
Naslov:
Zagotavljanje zunanjih ponudnikov storitev razvoja, uvajanja in vzdrževanja info...
Naročnik:
European Medicines Agency (EMA)
Datum objave v TED:
07/05/2020
Rok za prejem ponudb:
03/07/2020
Status:
Zaprto
Prikaži parametre filtra

Results per page: 10 | 25 | 50 146 Vprašanja found, displaying 61 to 70.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15 [Next/Last]
# Vprašanje Odgovor Zadnja objava Status
86
The document states that "describe how you would undertake a transformation of the application to a standard [...]
EMA’s long-term vision is to transform its’ overall IT-architecture towards software packages or software [...]
10/06/2020
85
Since the technical competencies and certificates of an IT Domain Expert will only be defined in the [...]
Your understanding is correct.
09/06/2020
84
For question 4.2 of the award criteria questionnaire, the tenderer is requested to describe how he would [...]
Examples of low-code SaaS/PaaS application platforms are Azure Dynamics365, Salesforce and SAP. The difference [...]
09/06/2020
83
With reference to section 19.2.1.b of the tender specifications, page 32, the tenderer shall provide [...]
Your understanding is not correct. For the evidence requested for 19.1.1 selection criteria, the tenderer [...]
09/06/2020
82
From our understanding, the "quality assurance" is to ensure the project and project members follow the [...]
Your understanding is correct. For Criterion 2 – Delivery approach – 2.4, we request the tenderer to [...]
09/06/2020
81
Our understanding is that project references need have been delivered during the minimum duration required [...]
Your understanding is not correct. References provided for 19.1.2 and 19.2.2. must refer to completed [...]
09/06/2020
80
Please expand what is meant by this statement - "Please reflect in your answer that the first release [...]
First release in production and following releases after Go-Live will be adopted by the National Competent [...]
09/06/2020
79
With reference to your question “ii. ensure continuity of the maintenance support including relevant [...]
Criterion 3 “ii. ensure continuity of the maintenance support including relevant policies and processes [...]
09/06/2020
78
With reference to your answer to Question #20, “The client references should demonstrate the tenderer [...]
The client references should demonstrate the tenderer’s ability to deliver whilst responsible for delivery [...]
09/06/2020
77
We understand that “Product Owners” in question 2.3 refer only to “Member States Product Owners” and [...]
User groups are described in section 3.3.2. of the technical specification, under: Member States Product [...]
09/06/2020