22
|
A comprehensive uplift/discount for all product groups is to be offered for each manufacturer mentioned [...]
|
As explained in the previous question, the uplift is a margin that the contractor is allowed to apply [...]
|
25/09/2019
|
|
2
|
Are we right in assuming that prices for one system each should be mentioned here? If not, please state [...]
|
You are right, the prices mentioned here are expected for one system each.
|
19/08/2019
|
|
3
|
Are we right in assuming that the limitation of 3 pages mentioned in point 3.5.4.2. also applies to the [...]
|
The limitation of 3 pages is only applicable to the 3 technical concepts described as Scenarios A, B [...]
|
19/08/2019
|
|
1
|
Are we right in assuming that the total price shown should reflect the initial infrastructure of 20 clients [...]
|
Indeed, the total price shown should reflect the initial infrastructure as described in section 1.3.1.1 [...]
|
19/08/2019
|
|
18
|
As regards the evidence that need to be provided under for Selection criterion 2.3 and more specific [...]
|
EDA confirms that the annex 4.9 need to be signed only by the Consortium leader in case of a Joint tender [...]
|
10/09/2019
|
|
6
|
Does EDA accept government information security approvals from NATO or EU Member States (e.g. NATO SECRET [...]
|
EDA is obliged to use equipment and vendors which have been approved and listed by the EU Council because [...]
|
19/08/2019
|
|
12
|
Does EDA intend to have a high availability / fail-over setup in terms of hardware?
|
As said in the general comment, the architecture and design of the future systems are fully open and [...]
|
19/08/2019
|
|
14
|
Does EDA intend to use printers across multiple domains/ classified systems in order to reduce its printer [...]
|
No, the classified systems must use dedicated printer hardware and there might be a requirement (subject [...]
|
19/08/2019
|
|
8
|
Does the classified EDA system need data from lower classified domains that it does not intend to share [...]
|
Yes, some data like updates of appliances or antivirus signatures will have to be transferred from an [...]
|
19/08/2019
|
|
20
|
Due to the broad scope of services requested and in order to prepare and submit the best possible offer [...]
|
The deadline for the receipt of tenders (“Receipt Time Limit”) is extended to 30/09/2019, at 10h00 (Brussels [...]
|
10/09/2019
|
|