Results per page: 10 | 25 | 50 33 Vprašanja found, displaying 21 to 30.[First/Prev] 1, 2, 3, 4 [Next/Last]
# Vprašanje Odgovor Zadnja objava Status
18
Section 2.2.3.1 requests that tenderers shall limit their technical offer to a maximum of 60 DIN A4 pages [...]
Yes, your understanding is correct.
08/05/2019
22
Section 1.4.2.1.4 asks that tenderers must submit use cases demonstrating phenological and productivity [...]
The aim of use cases is to provide evidence of the tenderer's ability to implement the envisaged service [...]
13/05/2019
19
With respect to the previously published Clarification answer #14, may we ask you to please further specify [...]
The minimum expected coefficient of correlation is +0.8, i.e. 80%, measured by the Pearson's correlation [...]
08/05/2019
28
In addition to Q/A No. 9… Task 5 specification in ToR is very general, so it is not fully clear (i) what [...]
Task 5 aims at setting up products which allow the best possible interoperability with vegetation products [...]
15/05/2019
27
In chapter 2.1, it is stated that "Each tenderer can only submit one offer. No tenderer may participate [...]
The statement in section 1.2 that each tenderer may only submit one offer does not apply to subcontractors [...]
15/05/2019
21
Dear Sirs You specify a 60 A4 page limit for the technical proposal; is this to include the requested [...]
The 60 DIN A4 pages is excluding CVs and project management information. Please also see question #18 [...]
10/05/2019
25
Here is a link provided in the ITT with reference to the HRLs [https://land.copernicus.eu/pan-european [...]
The requirement of "[...] (b) aligned to HRL files [...]" in sections 1.4.2.1.3 and 1.4.2.1.4 of the [...]
15/05/2019
24
To our understanding, the expected outputs shall be rasters for all tasks. How are these outputs expected [...]
It is correct that all outputs are raster files. The type of information provided within HR VPP will [...]
13/05/2019
26
From what is stated in this section, is it the output expected a WMS service?
Section 1.4.3 summarises the different type of data deliverables, not how files shall be disseminated [...]
15/05/2019
31
What is the expected number of users and/or volume of service use for the “Data dissemination/access” [...]
Copernicus land service currently counts nearly 40.000 registered users. Out of these, somewhat more [...]
21/05/2019