25
|
The presentation of 3 peer reviews of journal articles about full LCA assessment will meet the criteria [...]
|
Peer reviews of journal articles about full LCA assessment is not sufficient to meet the criteria you [...]
|
27/05/2013
|
|
24
|
Following the previous question (Number 11).Criteria relating to the tenders (Page 7): It is mentioned [...]
|
Yes
|
24/05/2013
|
|
23
|
Is there any template or table of content for the Technical offer?
|
No, there is no template available
|
24/05/2013
|
|
22
|
If the tenderer consist of more than one organization, does every single member of the tenderer has to [...]
|
YES. As clearly stated in the first sentence of Annex 6 - "Annex 6 has to be completed by all private [...]
|
17/05/2013
|
|
21
|
It is mentioned "coverage (geographical scope at least half of the one subject to this call for tender [...]
|
This requirement refers to projects involving actors from several countries and is independent from language [...]
|
17/05/2013
|
|
20
|
It is mentioned "the members of the team should have native-level or equivalent language skills" - what [...]
|
Language skills have to be strong enough in order to produce the e-learning package in the respective [...]
|
17/05/2013
|
|
19
|
It is mentioned "The tenderer must prove experience in carrying out trainings on Life Cycle Assessment [...]
|
The requirements clearly refer to Life Cycle Assessment, thus experience with "full" LCA trainings is [...]
|
17/05/2013
|
|
18
|
If the relevant experience in developing e-learning tools for the last 5 years could be part of the individuals [...]
|
Relevant experience is taken into account both in requirements related to the tenderer and to the team [...]
|
17/05/2013
|
|
17
|
It is mentioned that "tenderer must prove that he carried out at least 3 independent analyses of full [...]
|
Independent analysis means 3rd party review (i.e. the tenderer acted as a reviewer of an LCA study that [...]
|
17/05/2013
|
|
16
|
I understand that only the Lead needs to complete all forms in the case of subcontractors. However in [...]
|
Subcontractors must provide a letter of intent stating their willingness to provide the service foreseen [...]
|
17/05/2013
|
|
15
|
Hello, There are several Annexes that have to be completed i.e. 1-3 and 5. Can you provide these in word [...]
|
All these Annexes can be found in Word format on our tenders page on Europa: http://ec.europa.eu/environment [...]
|
16/05/2013
|
|
14
|
We note the paragraph re CVs on page 8 of the specification. Can you confirm that (a) we can provide [...]
|
Yes, you can provide your own style. We no longer request the Europass CV. No mandatory requirements [...]
|
16/05/2013
|
|
13
|
We have a French national staff member, but so far all our projects with French partners and customers [...]
|
You can apply. Please see in specifications: " the members of the team should have native-level or equivalent [...]
|
16/05/2013
|
|
12
|
Why is there besides English an explicit demand for French language skills and projects executed in French [...]
|
French language skills are needed because of the preparation of the e-learning package in French. There [...]
|
16/05/2013
|
|
11
|
In case of public projects funded by European Commission (FP7, LEONARDO, SUDOE, etc.) it is necessary [...]
|
You are asked to provide a List of relevant services/projects giving details of sums, dates and recipients [...]
|
16/05/2013
|
|
10
|
With regard to the criteria: "The tenderer must prove practical experience in the field of Life Cycle [...]
|
We ask for a "minimum" value if € 20.000 not for an "average" value of € 20.000.
|
16/05/2013
|
|
9
|
The tender refers to the development of e-learning packages. Could you confirm whether the contractor [...]
|
The tenderer/ contractor can choose any software for creating the e-learning package. Take into account [...]
|
16/05/2013
|
|
8
|
Please could you confirm or correct my interpretation of E-Learning needs. One e-learning package relating [...]
|
We are talking about 2 packages in total: 1 tailored around a specific PEFCR and 1 tailored around a [...]
|
16/05/2013
|
|
7
|
What kind of certificate would we need to provide as a Satisfactory Execution Certificate? Is it necessary [...]
|
There is no specific form or template for the certificate of Execution. This is usually in the form of [...]
|
15/05/2013
|
|
6
|
Can you please clarify what do you mean by “Among the different situations of exclusion, it is particularly [...]
|
NO, this clause is aimed at avoiding any evident conflict of interest which might cause a lack of trust [...]
|
08/05/2013
|
|
5
|
- Is it correct that the work of the help desk relates exclusively to those pilot projects that will [...]
|
This is not correct. The work of the helpdesk will support all pilots selected (i.e. both those lead [...]
|
07/05/2013
|
|
4
|
The TS states that the contractor will gather and store all the “results” provided by the participants [...]
|
This requirement refers particularly to the inventory data provided under confidentiality agreement. [...]
|
07/05/2013
|
|
3
|
Which requirements are put on the review process and on the reviewer qualification? Is the formal review [...]
|
The previous reply could be misleading. What is meant is that the contractor will not have to systematically [...]
|
07/05/2013
|
|
2
|
Is it correct that it will not be the responsibility of the contractor to develop new data sets (e.g. [...]
|
It will not be the responsibility of the contractor to develop new data sets. It will be the responsibility [...]
|
07/05/2013
|
|
1
|
'rules for pilot' mentioned on pg 12 paragraph 3.3 of the tender specifications document. Will this document [...]
|
Yes. Please Note the draft guidance documents referred to in the tender specifications have just been [...]
|
02/05/2013
|
|