65
|
According to SLA08, a financial penalty of 10% of the value of the affected assignment will be applied [...]
|
The objective of SLA08 is to ensure a sound and efficient administrative management, and to encourage [...]
|
18/01/2018
|
|
97
|
According to the chart of detailed expenses per contractor published on your website, Pomilio Blum, the [...]
|
The amount published covers both service fees and reimbursable costs. The cost split is strictly linked [...]
|
09/02/2018
|
|
71
|
According to the Technical Specifications (see Tender Specifications, page 21): The quality of services [...]
|
So far the customer satisfaction rate of EFSA’s events as defined in the tender specifications (“excellent [...]
|
19/01/2018
|
|
61
|
According to the Tender Technical Specifications, “Business disruption due to lack of business continuity [...]
|
As indicated in the footnote 35 of the tender specifications (pag 21) penalties will be deducted only [...]
|
18/01/2018
|
|
62
|
According to the Tender Technical Specifications: “Any environmental/operational/financial/project risks [...]
|
Risk management is a key principle in project management. The objective of SLA 05 is to ensure that risks [...]
|
18/01/2018
|
|
59
|
According to the Tender Technical Specifications: “EFSA may terminate the framework contract if: the [...]
|
Yes, your understanding is correct.
|
18/01/2018
|
|
60
|
According to the Tender Technical Specifications: “In case the Event Manager acting as single point of [...]
|
Designing and implementing business continuity plans is pivotal to ensure that a project is executed [...]
|
18/01/2018
|
|
101
|
Al fine di calcolare al meglio il singolo costo per partecipante richiesto nella financial offer siamo [...]
|
The price list item shall be selected on the basis of the total number of expected participants. For [...]
|
09/02/2018
|
|
84
|
As for the communication plan to be prepared for the test case, we would like to ask you the following [...]
|
The text case only requires the tenderer to recommend channels/tactics/tools to achieve the objectives [...]
|
20/01/2018
|
|
50
|
As per event outline, “approximately 20% of participants will be invited and reimbursed by EFSA (including [...]
|
The assumption is partially wrong. Only some of the people presenting a poster will be reimbursed (this [...]
|
10/01/2018
|
|
81
|
As per paragraph 1.2 - (21) Extra-muros assignments of Contractor’s staff, we understand that "Extra-muros [...]
|
As indicated in the corrigendum n°2 and clarification n°70, in case of contradiction the tender specifications [...]
|
19/01/2018
|
|
83
|
As per table in the tender spec (1.3), all tasks (including the Project Management and coordination activities [...]
|
The logic of reimbursable costs does not apply to price list items. As indicated in Paragraph 1.3, all [...]
|
20/01/2018
|
|
29
|
As per the Annex 3 - Draft Contract – point I.5.1-Maximum amount of the FWC and maximum prices: “The [...]
|
The maximum amount covering all purchases under this FWC, including all renewals and reimbursement of [...]
|
22/12/2017
|
|
79
|
As stated in the tender spec (1.3), all tasks can be subcontracted and so can be included into reimbursable [...]
|
The financial offer only covers the items that are listed in the table itself. Subcontracted costs (e.g [...]
|
19/01/2018
|
|
16
|
At paragraph 2.4A, "Selection criteria Economic and Financial Capacity", it’s stated that the 3 closed [...]
|
The evidence requested, in case of award, is the following: the annual accounts for the last 3 closed [...]
|
12/12/2017
|
|
1
|
Buongiorno, chiedo gentilmente cosa si intende nel dettaglio per il servizio richiesto di sicurezza: [...]
|
In delivering its services, the Framework Contractor will be required to comply with and act in full [...]
|
28/11/2017
|
|
44
|
Can the tenderer assume that EFSA will provide an access to its contact databases in order to invite [...]
|
The contractor will be given access to all information needed to carry out its tasks effectively and [...]
|
05/01/2018
|
|
4
|
Can you please tell us where the administrative data form, the legal entity form and the financial identifiy [...]
|
The administrative data, legal entity and financial forms can be uploaded in the section "Qualification [...]
|
01/12/2017
|
|
6
|
Can you tell us which documents are expected in the legal and regulatory capacity part of the e-submission [...]
|
For this specific open call, the legal and regulatory capacity part of the e-submission platform is not [...]
|
04/12/2017
|
|
30
|
Che tipo di Ritorno sull'Investimento (ROI) sugli eventi è richiesto? Qualitativo e/o qualitativo? E' [...]
|
As stated in the tender specifications, EFSA is seeking a provider that can act as a business partner [...]
|
22/12/2017
|
|
66
|
Could you clarify if the maximum available budget of 450k includes the renting of the venue and any other [...]
|
Yes, it is all inclusive.
|
18/01/2018
|
|
63
|
Could you clarify which of the two following proposals is penalised under the definition contained in [...]
|
Both above situations will give rise to SLA5 activation because, obviously, EFSA must be informed on [...]
|
18/01/2018
|
|
74
|
Could you confirm in view of all our previous questions that EFSA is conscious that it has designed and [...]
|
Please refer to answers provided to questions 59, 60, 61, 62, 63, 64, 65, 70, 71, 72, 73.
|
19/01/2018
|
|
27
|
Could you please confirm if the evidence requested at par. 2.4 for requirements a) [list of 5 events [...]
|
The evidence requested at par. 2.4 for requirements a), b) and c) should be uploaded in the e-submission [...]
|
19/12/2017
|
|
28
|
Could you please confirm if the Legal Entity Form has to be submitted only by the tenderer/Leader in [...]
|
The legal entity form and the financial identification form must be submitted only by the tenderer/ leader [...]
|
19/12/2017
|
|