29
|
Is it possible to delete the contractual penalty in Special Conditions, Article 1.8 as we feel this to [...]
|
The contractual penalty clause Art. I.8 of the Special Conditions is applicable. As set out in the preamble [...]
|
04/11/2019
|
|
28
|
Is our understanding correct, that the rights of EU under General Conditions, Article 11, are limited [...]
|
The acquisition of the intellectual property rights is limited to the rights on products created under [...]
|
04/11/2019
|
|
27
|
Is it correct that General Conditions, Article 9 defines only warranties covered and ruled by General [...]
|
Article 9 of the General Conditions concerns the contractual guarantee for the execution of the Contract [...]
|
04/11/2019
|
|
26
|
Is our understanding correct, that damages in General Conditions, Article 10 will be included in the [...]
|
Art. 1.8 of the Special Conditions sets out the specific rules for contractual penalties which apply [...]
|
04/11/2019
|
|
25
|
Is it correct, that the European Union undertakes to treat as confidential and not to disclose to any [...]
|
Your understanding is correct.
|
04/11/2019
|
|
24
|
- Please could you indicate whether work has to be performed in relation to the plan assets of the 5 [...]
|
Only two schemes have plan assets (JSIS and VPSMEP). There is no work to perform in relation with these [...]
|
24/10/2019
|
|
23
|
Based upon the document AO702 _Annex 2, Part B, the tasks 1-14 are related to the 5 different schemes [...]
|
The report on the methodological report shall be issued within the deadlines specified in Part B, Section [...]
|
24/10/2019
|
|
22
|
Based upon the document AO702 _Annex 2, Part B, we understand that VPSMEP was closed since 2009 and the [...]
|
As explained in Tender Specifications (Annex 2, Part B), new members cannot join the scheme since 2009 [...]
|
24/10/2019
|
|
21
|
Can we assume that the current plan rules will remain applicable or do you expect any changes in the [...]
|
We have not been informed of any changes that might occur during the lifetime of the contract.
|
24/10/2019
|
|
20
|
In Annex 2 on page 11 it is mentioned to submit the references (Annex form 6) with the tender, in Annex [...]
|
Yes, it is correct that the references (Annex form 6) regarding the technical and professional capacity [...]
|
24/10/2019
|
|