Uppgifter om anbudsinfordringar

Rubrik:
Multipelt ramavtal med förnyad inbjudan att lämna anbud för arkitekt- och ingenj...
Upphandlande myndighet:
European Border and Coast Guard Agency (Frontex)
Publiceringsdatum i TED:
28/12/2021
Sista anbudsdag:
07/02/2022
Status:
Stängd
Visa filterparametrar

Results per page: 10 | 25 | 50 24 Frågor found, displaying 1 to 10.[First/Prev] 1, 2, 3 [Next/Last]
# Fråga Svar Senaste publiceringsdag: Status
24
The provision is incomprehensible. Why should the contractor transfer its obligations to these persons [...]
The article II.7.3. shall read as follows: 3 The contractor must pass on information about all the relevant [...]
28/01/2022
23
We cannot accept unlimited liability for copyrights. Is it possible to negotiate this article?
The liability clauses are non-negotiable, however the thresholds of liability may be adapted.
28/01/2022
22
Will the contractor be entrusted with the processing of personal data under this contract? In our opinion [...]
There might be some data processed by the contractor like: name and surname of the person signing the [...]
28/01/2022
21
CBRE HQ is based in US. All of the project data are transferred to US. Is it possible to negotiate this [...]
Yes, the article may be adapted. Please note that under the documents section an updated Annex III to [...]
28/01/2022
20
Financial proposal - should we only provide prices for products and services listed in Annex IV? If so [...]
The floorbox's standard which should be priced in Financial Offer is the following: no carpet included [...]
28/01/2022
19
Financial proposal - according to the attachment IV, we should provide the rate per working hour of PjM [...]
The Annex IV Financial Offer template is limited to a few general positions that will be used to calculate [...]
28/01/2022
18
All of our invoices being raised in pdf format. It is our system requirement.
Article II.19.2 is only applicable if provided for in the special conditions. In this contract according [...]
28/01/2022
17
How much of the planned budget of EUR 3,200,000 for the project is to be allocated to works in the existing [...]
The majority of the planned budget is allocated for works in the current buildings leased by Frontex. [...]
27/01/2022
16
The subject of the RFP is providing Project Management and Architectural Services for specified works [...]
Yes, the subcontractors/builders will be selected by the Contractor.
27/01/2022
15
11. The GSM system works should be carried out by operator of the signal. That should not be done by [...]
Frontex would need the contractor to protect and secure devices during works, but in the event of floor [...]
27/01/2022