53
|
Considering that 28 October is a bank holiday in some countries: https://www.officeholidays.com/upcoming [...]
|
The Contracting Authority has decided to postpone the time limit for receipt of tenders to 4th November [...]
|
21/10/2019
|
|
56
|
Considering that 1st November is a bank holiday in some countries: https://www.officeholidays.com/upcoming [...]
|
The Contracting Authority has decided to postpone the time limit for receipt of tenders to 4th November [...]
|
21/10/2019
|
|
68
|
Concerning the supporting documents/evidence requested for 5.3. Selection of economic operators; Criterion [...]
|
The wording "This contract has been performed according to the contractual terms" is acceptable to us [...]
|
22/10/2019
|
|
29
|
Can you please confirm that we can cross-reference between questions in our reply in the technical tender [...]
|
There is no specific requirement regarding the format of the reply, as long as "The Technical proposal [...]
|
14/10/2019
|
|
28
|
Can you please confirm that it is not obligatory to propose resources with security clearance?
|
As stated in point 5.2. Security Clearance of the Technical Specifications, "All staff proposed by the [...]
|
14/10/2019
|
|
48
|
Can we please request an extension of the submission deadline by 1 week?
|
Please note that we do not consider extending the deadline. The deadline for the submission of tenders [...]
|
18/10/2019
|
|
9
|
Can the CA confirm that TM and QTM can be invoiced on a monthly basis?
|
As mentioned in the article 3.2 of ANNEX III of the modified Draft Framework Contract, the invoicing [...]
|
27/09/2019
|
|
4
|
At page 8 of the technical specifications, the RFP reads “Near shore: The Contractor will provide the [...]
|
We confirm that any location within the European Union is compliant.
|
26/09/2019
|
|
51
|
As part of the financial model, EEAS refer to 61 FTE’s. In the “technical specification” document page [...]
|
All figures are correct. 70 FTE (61 + 9) represents the “estimated number of FTE per year”, for the total [...]
|
21/10/2019
|
|
5
|
Art. I.6.3 point 2 of draft FWC. Why is the payment term 60 days?
|
As indicated in the said article of the draft FWC, the contracting authority decided to set the payment [...]
|
26/09/2019
|
|