Id-Dettalji tas-Sejħa għall-Offerti

Please note that in the eSubmission homepage (Tendering data) the valid tendering dates are those in the second blue banner: tender deadline 31/07/2020 16:00; Opening of tenders: 03/08/2020 11:00. The warning refers to the old date 11/06/2020. Tenders submitted within 31/07/2020 16:00 will be considered in time. IMPORTANT Published in Questions&Answers tab clarifications on issues with uploading p7m offer files.
It-titlu:
Modifika Retroattiva tas-Sistema tat-Triġenerazzjoni fis-sit ta' JRC Ispra bil-K...
L-Awtorità li Qiegħda Toħroġ il-Kuntratt:
European Commission, Joint Research Centre - Ispra (JRC-IPR)
Id-data tal-pubblikazzjoni tat-TED:
10/03/2020
Limitu ta' żmien għall-wasla tal-offerti:
31/07/2020
L-istatus:
Magħluq
Uri l-Parametri tal-Iffiltrar

Results per page: 10 | 25 | 50 180 Mistoqsijiet found, displaying 131 to 140.[First/Prev] 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18 [Next/Last]
# Mistoqsija It-tweġiba Data tal-aħħar pubblikazzjoni L-istatus
51
We ask to confirm that the extension of warranty is referred only to engines
Come indicato nel modello di offerta tecnica, l'estensione di garanzia èriferito al gruppo motore-generatore
22/05/2020
50
With reference to the clarification n. 5 published on May 4th, in the question the analysis of the reference [...]
La composizione chimica del gas naturale che alimenta l'impianto non è determinata dalla Commissione [...]
22/05/2020
49
Good morning, we ask you to confirm whether, with regard to the economic and financial requirements required [...]
Per ultimo bilancio chiuso si intende l’ultimo bilancio approvato alla data termine per la presentazione [...]
22/05/2020
48
is it possible to have more information regarding the existing boilers, chillers, heat pumps etc? In [...]
Technical documents and operating records are added to the tender documents
22/05/2020
47
As part of Scope of Work (SOW) of the Bidder the Client is kindly requested to clarify if the HVAC System [...]
The bidder is not requested to include in the bid the HVAC of the climatised areas of the building
22/05/2020
46
Regarding the redundancy of controller CPUs, have they to work together and compare their computation [...]
Please find redundancy requirements for CPU and I/O boards as per RE96001 – see §3.2, §4.1, §4.4. I/O [...]
22/05/2020
45
Is it possible to avoid the installation of the 30 barg compressors in case of electric starting systems [...]
The 30 barg compressor has been considered in the optic of the preliminary design. However, Contractor [...]
18/05/2020
44
Section 2.3.8.1 of the document labeled as “EN-03 – Financial offer form” states that a service walkways [...]
The indicated documents have been used as reference for the development of the preliminary design. Concerning [...]
18/05/2020
43
Is it possible to have technical datasheets regarding the existing water treatment systems (softener, [...]
A filtering, chlorination and demineralisation system exists. A technical sheet of the demineralisation [...]
18/05/2020
42
Is it possible to have additional information about the TLR network? Is the hot / chilled water flow [...]
The water in the TLR network is glycol-free.
18/05/2020