15
|
Please confirm that the maximum penalty for non-compliance with the specified deadline for a 10 man/day [...]
|
The application of penalties for non-compliance with the specified deadline will take into account working [...]
|
09/08/2019
|
|
14
|
Do the replacement terms imply that the team must be composed of at least two project manager profiles [...]
|
No. The composition of the team, as indicated in point 2.3 of the technical specifications, is as follows [...]
|
09/08/2019
|
|
13
|
Is the reimbursement travels by car systematically capped at the lowest price of the travel agency?
|
No.
|
09/08/2019
|
|
12
|
Between which locations is travel reimbursed? The headquarters or another office of the contractor? The [...]
|
Provided that it is stated in the service request that travel expenses will be reimbursed, the round [...]
|
09/08/2019
|
|
11
|
Please confirm that the number of working days is defined by the European Parliament in its request for [...]
|
Yes, each request for service from the European Parliament will detail the number of working days. No [...]
|
09/08/2019
|
|
10
|
Page 8 of the technical specifications. Do the contractors ranked second and third have to adapt themselves [...]
|
No, if the contractor ranked 1st is unable to perform the services, the contractor ranked 2nd will perform [...]
|
09/08/2019
|
|
9
|
Page 8 of the technical specifications. Does an active or passive refusal - or repeated refusal - by [...]
|
No. The contractor may be unable to perform the services without this resulting in the termination of [...]
|
09/08/2019
|
|
8
|
How do you assess whether price P could be evaluated as abnormally low, and that it does not distort [...]
|
The analysis of a price considered as abnormally low would be carried out in accordance with the principles [...]
|
09/08/2019
|
|
7
|
On page 5 of the technical specifications, "audits previously carried out" are mentioned. Will the evaluation [...]
|
Tenders are evaluated exclusively on the basis of the award criteria described on pages 16 and 17 of [...]
|
09/08/2019
|
|
6
|
The contract provides for three "cascade" framework contracts to be signed. Will the second and third [...]
|
No, the contractors ranked 2nd and 3rd will not be informed of the general activity of the contractor [...]
|
09/08/2019
|
|