Results per page: 10 | 25 | 50 87 Fragen found, displaying 41 to 50.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9 [Next/Last]
# Frage Antwort Datum der letzten Veröffentlichung Status
47
Could you please share the file/database design document for RDS Database and ‘Suspension from Trading [...]
Tenderers are requested to conduct the Function Point-analysis with what has been provided. They are, [...]
17/07/2015
46
a) Could you please provide us some examples of typical incidents that are in scope of the Lot1-SL2 technical [...]
Lot 1/SL2 • Monitoring alerts on servers (cpu, disk full) o Disk space alerts o CPU usage • Incidents [...]
16/07/2015
45
The Tender Specification document section 2.6 “General Constraints” says that all team members should [...]
Question already answered Q14.
16/07/2015
44
According to the Tender Specifications, the Contractor will provide for the needs of the Lot2 Contract [...]
ESMA confirms that this is generally correct. ESMA expects a growth in the area of business support which [...]
16/07/2015
43
With reference to Annex XIII- ‘Technical offer form’; Section 3.3. Proposed methods; Award question 7 [...]
This statement has been reworded in Annex XIII (track changes visible). An additional Annex is added [...]
16/07/2015
42
With reference to Annex XIII- ‘Technical offer form’; Section 3.2.1. Proposed organisation and infrastructure [...]
This was a clerical error and has been corrected in Annex XIII. Track changes visible.
16/07/2015
41
In the Annex IX page 5, the productivity matrix shows productivity category N°1 "Low/Small" and N°9 " [...]
The suggestion is taken on board, and Annex XIV has been updated accordingly to avoid confusion.
16/07/2015
40
The Category N°10 is defined as not being classified in the 9 productivity category. Therefore, not being [...]
Category 10 has been removed from Annexes XIV, IX and the tender specifications. Track changes visible [...]
16/07/2015
39
"See Annex IV for a full list of application ..." Could you please confirm that Annex XI "ICT system [...]
This was a clerical error. The correct Annex reference is indeed Annex XI. This has been corrected in [...]
16/07/2015
38
Productivity Category N°10 for Application maintenance is specified as "Low/Small" exactly as Category [...]
This was a clerical error. Category 10 has been removed from the financial offer form Annex XIV.
16/07/2015