247
|
In the context of Lot 5 Case Study 1, which areas should be covered in the organisational structure? [...]
|
The organisation structure must cover all the resources required for setting up the scope of the case [...]
|
10/09/2018
|
|
246
|
We understand that in this case study we need to explain the solution proposed, the plan to implement [...]
|
The implementation of the solution is included in the scope.
|
10/09/2018
|
|
245
|
We understand that with your answer to question #129 the scope of the answer does not include: how the [...]
|
I confirm your understanding.
|
10/09/2018
|
|
244
|
Regarding QA221, please note that some international organisations only sign certificates in their own [...]
|
See answer to Questions #121, # 122 and #221. The certificate of delivery shall be signed by the client [...]
|
10/09/2018
|
|
243
|
We understand that for finalised projects, the certificates should contain the following information: [...]
|
The required information are clearly listed in Annex 3 to Part G "Model of certificate of delivery". [...]
|
10/09/2018
|
|
242
|
With Reference to “EN-02A01B ITS19 - Part B to Technical Specifications - Profiles”, p. 38, Profile “ [...]
|
The CVs submitted for the tender's assessment for the L3-PITS profile must prove experience in any “processes [...]
|
10/09/2018
|
|
241
|
With Reference to “EN-02A01B ITS19 - Part B to Technical Specifications - Profiles”, p. 44, Profile “ [...]
|
Please, refer to the answer to Question83
|
10/09/2018
|
|
240
|
Regarding QA 116 where you confirm that “all references together should address all the technical areas [...]
|
The set of references must demonstrate that the tenderer is able to address all the technical areas covered [...]
|
10/09/2018
|
|
239
|
Regarding QA 116 where you confirm that “all references together should address all the technical areas [...]
|
The set of references must demonstrate that the tenderer is able to address all the technical areas covered [...]
|
10/09/2018
|
|
238
|
Your answer to question number 156: “[…] The maintenance part of the project should be excluded from [...]
|
Your understanding is correct.
|
10/09/2018
|
|