According to section “5.1.3 Hand-over” of the Questionnaire, the contractor is called to show its plan [...]
|
We do confirm a clerical mistake. Section “5.1.3 Hand-over” of the Questionnaire should read: "Its proposed [...]
|
20/03/2017
|
|
29
|
According to the WP2 Take-over, included in “Annex 2b: Technical Annex”, the contractor is called to [...]
|
The QA3 Hand-over Plan will be requested to the existing contractor once the results of QA4 Call for [...]
|
20/03/2017
|
|
23
|
Are we correct in assuming that the information requested in Chapter 4.2 of the questionnaire is to be [...]
|
Yes the information is to be provided in Attachment 1 - Service Reference Form of the Questionnaire.
|
20/03/2017
|
|
17
|
Article 1.5.1 of the General Terms and Conditions refers to Article II.4 of the General Conditions. Unless [...]
|
We confirm, the correct reference should be to Article II.15. A new version of the model contract is [...]
|
15/03/2017
|
|
32
|
As per your answer n° 19, can you please confirm that the tenderer can rely on references of its affiliated [...]
|
No we do not confirm; our reply to Q19 was incomplete and should be read as follows : 1) As per Art 146.5 [...]
|
24/03/2017
|
|
26
|
Can you confirm that travels that can be requested in the context of the QA4 activities (Missions, audits [...]
|
We do confirm that travels will be requested in the context of QA4 activities (missions, audits, QC of [...]
|
20/03/2017
|
|
11
|
Concerning paragraph 1.2.12 of the Questionnaire, please confirm that in case of a joint tender only [...]
|
We do not confirm. Section 1.2 clearly indicates that it must be completed as many times as there are [...]
|
15/03/2017
|
|
30
|
Due to the fact that the column width is blocked, the totals are not visible and show as #########. Can [...]
|
The column "Estimated budget TOTAL" of sheet TBP has been extended. An updated Price Table is published [...]
|
24/03/2017
|
|
28
|
In case of services provided to a private purchaser certified by the service provider through a declaration [...]
|
We do confirm that the client contact is mandatory. As stated in Section "4.2.1. Client References (Mandatory [...]
|
20/03/2017
|
|
2
|
In order to allow an accurate price calculation of the FAT work Package (WP.9.6.1A & WP.9.6.1B), [...]
|
WP.9.6.1A: average duration: 15 days (possibly with interruptions) WP.9.6.1B: average duration: 2 days [...]
|
15/03/2017
|
|