a. How many users will need to have access to those systems on Commission’s behalf? b. Please, confirm [...]
A: See reply to question #37 B: Regular monitoring of the helpdesk's activities will be ensured by the [...]
12/11/2018
Answered
59
According to Annex 2, we understand that for the Level I, II and III CVs the university degree is not [...]
See reply to question 58
21/11/2018
Answered
65
According to the answer 61: "All experts defined in Annex II (Qualification levels I to IV) will hold [...]
See replies to questions 30 and 31
29/11/2018
Answered
76
According to the specification of the CfT, there appear two different sets of reports: (Section 1.2.4 [...]
Both lists are correct and complement each other. Section 1.2.4 explains delivery from the payments perspective [...]
10/12/2018
Answered
3
According to the Tender Specifications, we need to provide references in English, German, French, Italian [...]
The evidence to fulfil criterion A2 consists of references for actions (projects or services) delivered [...]
02/10/2018
Answered
23
According to the Tenderer Specifications, we need to provide references showing the provision of helpdesk [...]
Please see reply to question #10
12/10/2018
Answered
10
According to the Tenderer Specifications, we need to provide references showing the provision of helpdesk [...]
The tenderer must provide references showing the provision of helpdesk services. Only services provided [...]
05/10/2018
Answered
26
According to the tendering specifications we read that all the evidence concern the Selection Criteria [...]
The tenders must be presented as follows (section 1.6): Part A: Identification of the tenderer Part B [...]
12/10/2018
Answered
44
Can the contracting authority confirm alternative contact methods are funded separately by them or should [...]
The Contracting Authority expects the future Contractor to provide equivalent contact services to the [...]
07/11/2018
Answered
40
Can the Contracting Authority explain how access to the JIRA based ticketing system will be provided [...]
The Contracting Authority will provide the Contractor with the necessary credentials (username and password [...]