1
|
'rules for pilot' mentioned on pg 12 paragraph 3.3 of the tender specifications document. Will this document [...]
|
Yes. Please Note the draft guidance documents referred to in the tender specifications have just been [...]
|
02/05/2013
|
|
5
|
- Is it correct that the work of the help desk relates exclusively to those pilot projects that will [...]
|
This is not correct. The work of the helpdesk will support all pilots selected (i.e. both those lead [...]
|
07/05/2013
|
|
6
|
Can you please clarify what do you mean by “Among the different situations of exclusion, it is particularly [...]
|
NO, this clause is aimed at avoiding any evident conflict of interest which might cause a lack of trust [...]
|
08/05/2013
|
|
24
|
Following the previous question (Number 11).Criteria relating to the tenders (Page 7): It is mentioned [...]
|
Yes
|
24/05/2013
|
|
15
|
Hello, There are several Annexes that have to be completed i.e. 1-3 and 5. Can you provide these in word [...]
|
All these Annexes can be found in Word format on our tenders page on Europa: http://ec.europa.eu/environment [...]
|
16/05/2013
|
|
16
|
I understand that only the Lead needs to complete all forms in the case of subcontractors. However in [...]
|
Subcontractors must provide a letter of intent stating their willingness to provide the service foreseen [...]
|
17/05/2013
|
|
18
|
If the relevant experience in developing e-learning tools for the last 5 years could be part of the individuals [...]
|
Relevant experience is taken into account both in requirements related to the tenderer and to the team [...]
|
17/05/2013
|
|
22
|
If the tenderer consist of more than one organization, does every single member of the tenderer has to [...]
|
YES. As clearly stated in the first sentence of Annex 6 - "Annex 6 has to be completed by all private [...]
|
17/05/2013
|
|
11
|
In case of public projects funded by European Commission (FP7, LEONARDO, SUDOE, etc.) it is necessary [...]
|
You are asked to provide a List of relevant services/projects giving details of sums, dates and recipients [...]
|
16/05/2013
|
|
2
|
Is it correct that it will not be the responsibility of the contractor to develop new data sets (e.g. [...]
|
It will not be the responsibility of the contractor to develop new data sets. It will be the responsibility [...]
|
07/05/2013
|
|