1
|
1. The “Estimates for Work area 2 - ICT BackOffice” in tender specifications section 2.2.5.5 are summing [...]
|
1. The estimations in the work area Backoffice under 2.2.5.5. indeed add up to 101% due a rounding error [...]
|
22/01/2018
|
|
40
|
a. Could you please clarify whether business/application support (e.g. “how to” questions, assistance [...]
|
Business and application support services will be provided by other parties than the future contractor [...]
|
06/02/2018
|
|
39
|
a. Could you please clarify whether the scope of this call for tenders includes the need for onsite intervention [...]
|
Part of the ICT BackOffice services activity (Work area 2) the profile Server Administrator might in [...]
|
06/02/2018
|
|
54
|
According to the answer to question 11, the team is to be described in the Service Delivery Plan. Should [...]
|
Sample CVs for each profile will be required for the technical and professional capacity. For the SDP [...]
|
13/02/2018
|
|
66
|
According to the Tender Specifications (page 13) “1. All contractor’s consultants working for ECDC need [...]
|
This question is answered already in question #9.Question9
|
15/02/2018
|
|
61
|
Annex VI – Tender Submission Checklist: - “The duly completed Authorised Signatory Form…” - “The duly [...]
|
Yes your understanding is correct.
|
14/02/2018
|
|
63
|
Annex VI – Tender Submission Checklist: “You should also ensure that: Both the technical and financial [...]
|
The technical proposal as specified in the Tender Specifications (see 4.1) shall also be signed, with [...]
|
14/02/2018
|
|
60
|
Annex VII - e-Submission application guide par. 1.2. Documents to be signed and dated while creating [...]
|
Yes your understanding is correct.
|
14/02/2018
|
|
52
|
Are all the KPIs described in Chapter 8 measurable with existing ITSM tools?
|
Many KPIs, especially in the area of incident and request management, can be measured with the ITSM. [...]
|
13/02/2018
|
|
56
|
BO13 (recommended)There should be no bugs found in production related to integration that were not detected [...]
|
Please note that the testing covers only integration testing and not full functional (business) testing [...]
|
13/02/2018
|
|
8
|
Can you please give detailed information about the applications to host within this FwC, regarding data [...]
|
You find information about the hosting service provided by the Backoffice team under 2.2.4.2 in the tender [...]
|
25/01/2018
|
|
69
|
Can you provide any rough estimation of the expected estimated annual workload? Can you provide us with [...]
|
ECDC will not give additional information on addition to 2.2.3.3 on the number of changes to handle, [...]
|
15/02/2018
|
|
64
|
Can you share with us the Annex IX - Data protection agreement which is not provided with the tender [...]
|
The data protection agreement is part of the draft framework contract, page 58.
|
14/02/2018
|
|
72
|
Dear Procurement Team, Under section “2.2.3.4 Service level management” one of the listed activities [...]
|
Currently we operate under compliance with No 45/2001 and in the future with the GDPR. In practise the [...]
|
19/02/2018
|
|
5
|
Do you confirm that the estimation of the annual workload in man-hours (for instance 90 for the frontoffice [...]
|
It is correct, the right column gives an indication of work hours outside office hours and outside the [...]
|
22/01/2018
|
|
3
|
Doc “Tender Specifications”, pg 28: Profiles required: “Server Administrator” but in “Technical Annex [...]
|
The profile name “Server administrator” and “System administrator” should be read as equivalent. In the [...]
|
22/01/2018
|
|
71
|
Does ECDC allow Contractor to use it own ITIL support management system ? The support system to comply [...]
|
Please read on page 15 under 2.2.2.4: “The contractor will be responsible to maintain and update the [...]
|
19/02/2018
|
|
70
|
Does ECDC deliver the services with internal resources or external suppliers beside those stated on page [...]
|
On 2.1 we give an overview how ECDC IT service internally is organised and about of the other contracts [...]
|
19/02/2018
|
|
51
|
ECDC says it have some Printer MFP, Should the contractor cover hardware and maintenance of those as [...]
|
The contractor should NOT cover hardware and maintenance for the MFDs. That will be provided by the printer [...]
|
13/02/2018
|
|
53
|
In 2.2.7.4 (tender specification) on site and off site work ECDC state that will be 4+1 seat however [...]
|
ECDC is currently moving to new premises and expect that 5 seats will be available for the suppliers [...]
|
13/02/2018
|
|
48
|
In answer 41, you wrote "The main intention is that (...) all the providers staff (...)". But in the [...]
|
Ideally we see all consultants here once in a while, but practically the positions required for local [...]
|
09/02/2018
|
|
55
|
In KPI BO13(many is called the same) Every completed test must have a test report. Question 1: Can you [...]
|
Indeed the testing activities are described in 2.2.3.8 of the tender specifications.
|
13/02/2018
|
|
49
|
In section 3.2.3 (Technical and Professional Capacity) of the Tender Specifications, it is requested [...]
|
Your assumption is fully correct. The description of the tenderer's professional activity should be 3 [...]
|
09/02/2018
|
|
10
|
In the case of 18 penalty points (and higher) no other consequence than "Possible termination of FWC" [...]
|
It is correct, in the situation of 18 or more penalty points and that ECDC would not cancel the FWC, [...]
|
26/01/2018
|
|
50
|
In the event a tenderer (main contractor) intends working with one (or more) subcontractor(s) for the [...]
|
From the list of documents mentioned, you can provide for each subcontractor the 'LOI to Collaborate' [...]
|
09/02/2018
|
|