18
|
1. According to the tender specifications (paragraph 3.2.1) “the tenderer should specify in the framework [...]
|
a)The participation of a partner of a Consortium to a research funded project under a European programme [...]
|
25/03/2015
|
|
19
|
2. According to the tender specifications (paragraph 3.1) : “the objective of this multiple Framework [...]
|
The required services are in the areas of policy and technical analysis and will be delivered in the [...]
|
25/03/2015
|
|
12
|
According to tender specifications, technical offer is based on hypothetical scenario described in Section [...]
|
The members of the consortium must be identified as explained in section 1.6 of the tender specifications [...]
|
16/03/2015
|
|
13
|
Can a company participate in multiple consortia as subcontractor or partner?
|
There are no specific rules in the Financial Regulation or the Implementing Rules forbidding explicitly [...]
|
16/03/2015
|
|
2
|
Can be the total offered price for the Framework Contract lower than 15.000.000€?
|
The amount indicated in section 2.6.2 refers to the global estimated budget of the framework contract [...]
|
06/03/2015
|
|
7
|
Could you please confirm that the % of discount that will be offered in each specific request for service [...]
|
As explained in section 2.6.1 if the Tender Specifications “The unit prices (person-days) given in the [...]
|
13/03/2015
|
|
10
|
Dear Sirs, Regarding the requirement mentioned under Point 2.3.2.3 (evidence to be provided for selection [...]
|
Your interpretation is correct, the documentation requested shall proof the educational and professional [...]
|
13/03/2015
|
|
15
|
Dear, The team delivering the service should consist of four different type of profiles (Team coordinator [...]
|
Only the profiles listed in section 2.3.2.2 of the Tender Specifications will be assessed to verify the [...]
|
19/03/2015
|
|
3
|
Financial evaluation will be based on unit prices provided for each category of experts or on the overall [...]
|
As stated in section 2.6 of the Tender specifications “The total amount (total 1 + total 2) quoted in [...]
|
06/03/2015
|
|
6
|
If evaluation of financial offer is based on the overall value offered for the hypothetical scenario, [...]
|
We confirm that as stated in section 2.6.1 of the tender Specifications “The total amount (total 1 + [...]
|
13/03/2015
|
|