30
|
In Question 19 you state that 'prices tendered for shall include all the costs to be incurred by the [...]
|
(a) Technical infrastructure means hardware and software needed for developments in Proximity and Near [...]
|
14/10/2019
|
|
19
|
In Question 3.3 Annex 5 of technical specifications it is requested to specify the necessary technical [...]
|
The award sub-criterion 3.3 requests to specify “How you will ensure that the technical infrastructure [...]
|
08/10/2019
|
|
18
|
In Question 3.4 Annex 5 of technical specifications, can you please confirm our understanding that the [...]
|
Award sub-criterion 3.4 refers to both types of Services: Time and Means and Quoted Time and Means.
|
08/10/2019
|
|
45
|
In reference to Q&A 2, can you please confirm that the illustrative example of Q.3.2 can also be [...]
|
We expect practical examples illustrating tenderers' answer. These examples do not need to be complete [...]
|
17/10/2019
|
|
61
|
In regards to evidence in economic and financial capacity, we understand that entities relied upon will [...]
|
Your understanding is correct.
|
21/10/2019
|
|
50
|
In relation to the page limitation - 80 pages, is it allowed to have some graphs in the 80 pages at reduced [...]
|
All graphs will be counted within the 80-page limit. However, we accept that some graphs at reduced size [...]
|
21/10/2019
|
|
40
|
In technical tender award sub-criterion 2.1 you mention "processes, interfaces, responsibilities, structure [...]
|
Processes is a generic term referring here to the manner in which the work/activities/information/knowledge [...]
|
17/10/2019
|
|
13
|
In the document Request to participate form, page 4, list of previous contracts, Our understanding is [...]
|
Yes, your understanding is correct.
|
01/10/2019
|
|
14
|
In the document Request to participate form, page 4, list of previous contracts, value in the currency [...]
|
The tenderers have to include the contract value during the past three calendar years (for which accounts [...]
|
01/10/2019
|
|
63
|
In the document Request to participate form, section 6 Technical and professional capacity, table list [...]
|
Please note that if the currency of your contracts is EUR and you have filled in the column "value in [...]
|
22/10/2019
|
|
37
|
In the e-Submission platform, in the Tender offer step, the following fields are mandatory: Total amount [...]
|
As indicated in the e-Submission Quick guide in tender specifications point 3, you must fill in the total [...]
|
17/10/2019
|
|
36
|
In the invitation to tender we read: The hand-signed originals (Tender report and Declaration on Honour [...]
|
Yes, we confirm that the hand-signed originals must be sent to the European External Action Service, [...]
|
17/10/2019
|
|
67
|
In the quality award criteria you request for our approach for the first specific contracts of the first [...]
|
The Contracting Authority will decide on and request the services at the start of the framework contract [...]
|
22/10/2019
|
|
7
|
In the Tender Specifications, Section 5, Criterion 5.3.3.a), Minimum capacity level, p. 8, we read “At [...]
|
We confirm that all the mentioned examples are considered acceptable.
|
26/09/2019
|
|
8
|
In the Tender Specifications, Section 5, Criterion 5.3.3.a), Minimum capacity level, p. 8, we read “Each [...]
|
We confirm that your understanding is correct.
|
26/09/2019
|
|
73
|
In your answer to question 19, you ask Tenderers to take into account in their prices all costs associated [...]
|
We confirm the answer to question 19. As stated in the Tender Specifications (in point 6.3 Financial [...]
|
30/10/2019
|
|
35
|
Is the EEAS expecting a full Service Management Quality Plan (SMQP) in this answer? Or is the EEAS only [...]
|
The description of your proposal of SMQP does not need to be long, but should provide enough information [...]
|
17/10/2019
|
|
15
|
Is the understanding that FWC will be awarded to a single economic operator and that it does not imply [...]
|
Indeed, the understanding is correct. The framework contract will be awarded to a single economic operator [...]
|
03/10/2019
|
|
34
|
It is our understading that the description of the tender is not included in the page limit of 80 pages [...]
|
The description of the tender will be counted within the 80-page limit. Regarding the 80-page limit, [...]
|
17/10/2019
|
|
17
|
On Question 3.5 Annex 5 of the technical specifications, can you please confirm our understanding that [...]
|
The award sub-criterion 3.5 requests to “specify which measures, tools and processes you commit to implement [...]
|
08/10/2019
|
|
60
|
Our understanding is that in case of a joint offer with envisaged subcontracting, the “Legal Entity Form [...]
|
A legally constituted consortium must present its own Legal Entity Form (LEF) which is different from [...]
|
21/10/2019
|
|
44
|
Our understanding is that the cover, table of contents and question description are not counted in the [...]
|
The cover and table of contents are not counted in the limit of 80 pages.
|
17/10/2019
|
|
3
|
Our understanding is that the financial identification form must be submitted by the leader of the consortium [...]
|
Yes, your understanding is correct.
|
25/09/2019
|
|
59
|
Our understanding is that the original hardcopies of the signed Tender Report and the Declaration on [...]
|
When the declaration(s) on honour and/or the tender report are signed by hand, a scanned copy must be [...]
|
21/10/2019
|
|
6
|
Our understanding is that there are no CVs to be submitted at tender submission deadline (28/10/2019) [...]
|
We confirm there are no CVs to be submitted at tender submission deadline (28/10/2019).
|
26/09/2019
|
|