49
|
Could you please explain the reason why C equals 5 for WKP2 of Phase 1 and equals 10 for WKP2 of Phase [...]
|
The constant C was considered to take into account the specific situation in WKP/phase. Please, see the [...]
|
20/06/2019
|
|
13
|
Could you please indicate the duration of the meetings?
|
The duration of the meetings are not expected to last more than 1 (one) working day per face to face [...]
|
19/06/2019
|
|
21
|
Could you please indicate the maximum number of Authorisation Tickets (Certificates) in case that the [...]
|
CORRIGENDUM: INSTEAD OF 'Annex I - Part 2: Technical Specifications does not define a maximum amount [...]
|
20/06/2019
|
|
31
|
Could you please provide the definition of "compliance assessment criteria"
|
Compliance/conformity assessment is to be interpreted as defined in the main part of the C-ITS Delegated [...]
|
20/06/2019
|
|
29
|
Could you please provide the number of 'of end-entities’ subscriber organisations?
|
This is not defined at this moment as it is based on market demand. It is foreseen that the Specific [...]
|
20/06/2019
|
|
30
|
Could you please provide the number of C-ITS station types?
|
This is not defined at this moment as it is based on market supply of C-ITS stations.
|
20/06/2019
|
|
27
|
Could you please provide the percentage breakdown of fixed and mobile C-ITS stations?
|
The percentage breakdown is not defined at this moment as it will depend on the market demand. It is [...]
|
20/06/2019
|
|
4
|
Dear Sirs, Please indicate the section of the Call from tender from where we could download the following [...]
|
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
|
19/06/2019
|
|
1
|
Dear, Could you make the documents available for download, as I can only see the Invitation Letter? Kind [...]
|
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
|
19/06/2019
|
|
35
|
Following is written in clause II.6.3: The contractor is liable for any loss or damage caused to the [...]
|
With reference to Article II.6.3. we confirm that the "total amount of the contract" does refer to the [...]
|
20/06/2019
|
|
91
|
From the answer to Question 90 we assume that a new deadline will be defined for the tender. Since tender [...]
|
The deadline will be postponed, The postponement will be published in a corrigendum of the e notice, [...]
|
19/07/2019
|
|
3
|
Good day, where can I download the tender specification of the above mentioned tender? Thank you.
|
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
|
19/06/2019
|
|
8
|
I don't find the documents and the tender specifications with their respective annexes, where I can find [...]
|
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
|
19/06/2019
|
|
11
|
In Annex B to the Annex 1 - Part 1 to the contract: Administrative Annex: "21 AA / EA per year" is referenced [...]
|
In Annex I – Part 2 Technical Specifications, page 10, 2.2. Scalability requirements – Phase 2: 20 AAs [...]
|
19/06/2019
|
|
24
|
In document "EN-05 Annex I Part 2 Technical Specifications", chapter "2.2. Scalability requirements", [...]
|
For the purpose of Phase 2 in the evaluation table, the number of 21 is only indicative to provide an [...]
|
20/06/2019
|
|
76
|
In order to be compliant to point 8 from Annex 3 “Compliance Audit And Other Assessments” and in particular [...]
|
The Certificate Policy, which is [1] of Annex I to the Contract - Part 2: Technical Specifications, defines [...]
|
09/07/2019
|
|
74
|
In order to follow all the requirements specified in the Tender Documentation is possible to Have a specific [...]
|
We do not see a need for an additional communication network to be setup between the different environments [...]
|
09/07/2019
|
|
43
|
IN ORDER TO SUBMIT A COMPETITIVE FINANCIAL AND TECHNICAL OFFER AND TO PRODUCE ALL DECLARATIONS REQUESTED [...]
|
Kindly note that a corrigendum of official journal will be published soon.
|
20/06/2019
|
|
77
|
In reference to the policy document cellar_9a2fe08f-4580-11e9-a8ed-01aa75ed71a1.0005.02_DOC_4.pdf, we [...]
|
The three mentioned environments should be fully separated, we do not see a way to centrally manage log [...]
|
09/07/2019
|
|
38
|
In relazione alla procedura di cui in oggetto ed al termine ultimo fissato per la presentazione della [...]
|
Vi informiamo cha a breve sarà pubblicata la rettifica della Gazzetta ufficiale.
|
20/06/2019
|
|
23
|
In terms of "interacting with the Accredited Auditors" can the JRC clarify whether CA compliance audits [...]
|
We confirm that the contractor will be responsible for the entire process of auditing the EU Root CA, [...]
|
20/06/2019
|
|
6
|
In the Document Library only the Invitation letter is available, do you expect to upload the Tender specifications [...]
|
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
|
19/06/2019
|
|
80
|
In the EN-04 Financial offer Evaluation table, more exactly in the row 25, Base services provision, is [...]
|
The second phase of the contract is regulated by a framework contract, and services will be ordered by [...]
|
11/07/2019
|
|
87
|
In the Evaluation table row 25, could you please indicate which costs should the provider insert?
|
The base service provisions include the costs for the support for the EU Root CA, internal EA and AA [...]
|
16/07/2019
|
|
14
|
Is it correct to assume that the external EA or AA must satisfy the Certificate Policy (CP) requirements [...]
|
No, we do not consider that a correct assumption. The contractor will have to define the EU root CA’s [...]
|
19/06/2019
|
|