29
|
Can you please confirm that we can cross-reference between questions in our reply in the technical tender [...]
|
There is no specific requirement regarding the format of the reply, as long as "The Technical proposal [...]
|
14/10/2019
|
|
68
|
Concerning the supporting documents/evidence requested for 5.3. Selection of economic operators; Criterion [...]
|
The wording "This contract has been performed according to the contractual terms" is acceptable to us [...]
|
22/10/2019
|
|
56
|
Considering that 1st November is a bank holiday in some countries: https://www.officeholidays.com/upcoming [...]
|
The Contracting Authority has decided to postpone the time limit for receipt of tenders to 4th November [...]
|
21/10/2019
|
|
53
|
Considering that 28 October is a bank holiday in some countries: https://www.officeholidays.com/upcoming [...]
|
The Contracting Authority has decided to postpone the time limit for receipt of tenders to 4th November [...]
|
21/10/2019
|
|
57
|
Considering that both 28th of October and Friday1st November is a bank holiday in some countries: https [...]
|
Please note that we do not consider extending again the deadline. The deadline for the submission of [...]
|
21/10/2019
|
|
62
|
Either party may terminate the FWC and/or the FWC and all or certain specific contracts by sending formal [...]
|
After thorough analysis of the new drafting proposed, the Contracting Authority came to the conclusion [...]
|
21/10/2019
|
|
10
|
How are quarterly measured LDUs linked to monthly invoices and monthly supporting Service Acceptance [...]
|
As indicated in SLA (Chapter 3.), the liquidated damages are calculated on a quarterly basis. Similarly [...]
|
27/09/2019
|
|
66
|
How is the Phase-In, transition to be invoiced? Will it be treated as a separate project and to be budgeted [...]
|
The Contracting Authority will decide on and request the services at the start of the framework contract [...]
|
22/10/2019
|
|
71
|
In Annex 10 of the Technical specifications, there is a Daily Activity Assistant (DAM) foreseen (Chapt [...]
|
It is up to the Contracting Authority to decide, during the execution of the contract, to request or [...]
|
25/10/2019
|
|
65
|
In Annex 8 to technical Specifications (SLA) there is in KPI-1 (4.1. Ordering process) a compensation [...]
|
For KPI-1, liquidated damages apply, among other cases, in case "the candidate is […] declared unable [...]
|
22/10/2019
|
|