25
|
We would like to request the extension of the submission deadline, considering that the offer is complex [...]
|
Considering that (1) The time-limit for receipt of tenders is minimum 42 days and that the Contracting [...]
|
20/03/2017
|
|
15
|
We understand that §§2, 3 and 4 of article II.18.4 of the General Conditions for the framework contract [...]
|
Your understanding is incorrect. The second, third and fourth paragraphs of Article II.18.4 fully apply [...]
|
15/03/2017
|
|
3
|
We understand that the envelope constituting the Financial tender must consist of Section 6 from the [...]
|
- The envelope constituting the Financial tender should only contain the Price table (Annex 3). - On [...]
|
15/03/2017
|
|
24
|
We posted a number of questions on the portal, can you confirm the estimated time of response of these [...]
|
The replies to these questions have been answered on 15/03/2017
|
20/03/2017
|
|
21
|
We notice a considerable difference between the volumes in the historical baseline, compared to the volumes [...]
|
The increase of volumes is not caused by the introduction of the proportionality principle. The justification [...]
|
20/03/2017
|
|
16
|
Under article II.23.2 of General Conditions for the framework contract, the contracting authority has [...]
|
your understanding is correct
|
15/03/2017
|
|
31
|
There are only 35 lines to enter profiles in the Profile Pi Pricing sheet of the price table. Can this [...]
|
No; tenderers can indicate maximum 35 profiles
|
24/03/2017
|
|
22
|
The Technical Annex2.B describes that no daily reports are requested in scope of WP.9.5.2 (quality control [...]
|
We do confirm that no daily reports are requested for Category 1 conformance tests. The average duration [...]
|
20/03/2017
|
|
33
|
Regarding to the contract notice with No: 2017/S 032-057176 dated on 15.02.2017 under the name "Belgium [...]
|
As indicated in the contract notice under the section IV.1.8, this procedure is covered by the Agreement [...]
|
24/03/2017
|
|
7
|
Regarding pages 11 and 12 from Annex 4 “Guidebook for Tenderers”, section 6.4.3. “Elements to be separated [...]
|
Folder 1 must contain 1 original + 2 copies of - all documents related to Annex 1 - Questionnaire pages [...]
|
15/03/2017
|
|