Information om udbud

Titel:
ISDLS2 — Levering af eksterne tjenesteydelser til udvikling, vedligeholdelse og ...
Ordregivende myndighed:
European External Action Service (EEAS)
Dato for offentliggørelse på Ted:
19/09/2019
Frist for modtagelse af bud:
04/11/2019
Status:
Lukket
Vis filterindstillinger

Results per page: 10 | 25 | 50 74 Spørgsmål found, displaying 51 to 60.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8 [Next/Last]
# Spørgsmål Svar Senest offentliggjort Status
25
In point 6.1.3 of technical specifications you request that the resources of the Contractor record their [...]
ITAM is an activity monitoring tool and does not serve the same purpose as a badging system. As indicated [...]
11/10/2019
27
In point 3.5 of the technical specifications you group the profiles under four (4) Technical teams. This [...]
As stated in Technical Specifications point 2.7 Technical teams and Project Teams, activities can be [...]
11/10/2019
32
In Part II technical specifications, point 2.4 Place of Delivery there it is mentioned that for Proximity [...]
(a) and (b): As stated in the Tender Specifications (6.3. Financial Tender), "the prices are all inclusive [...]
15/10/2019
23
In order to submit a high quality response, can we request an extension of the deadline by 15 days to [...]
Please note that we do not consider extending the deadline. The deadline for the submission of tenders [...]
11/10/2019
65
In Annex 8 to technical Specifications (SLA) there is in KPI-1 (4.1. Ordering process) a compensation [...]
For KPI-1, liquidated damages apply, among other cases, in case "the candidate is […] declared unable [...]
22/10/2019
71
In Annex 10 of the Technical specifications, there is a Daily Activity Assistant (DAM) foreseen (Chapt [...]
It is up to the Contracting Authority to decide, during the execution of the contract, to request or [...]
25/10/2019
66
How is the Phase-In, transition to be invoiced? Will it be treated as a separate project and to be budgeted [...]
The Contracting Authority will decide on and request the services at the start of the framework contract [...]
22/10/2019
10
How are quarterly measured LDUs linked to monthly invoices and monthly supporting Service Acceptance [...]
As indicated in SLA (Chapter 3.), the liquidated damages are calculated on a quarterly basis. Similarly [...]
27/09/2019
62
Either party may terminate the FWC and/or the FWC and all or certain specific contracts by sending formal [...]
After thorough analysis of the new drafting proposed, the Contracting Authority came to the conclusion [...]
21/10/2019
57
Considering that both 28th of October and Friday1st November is a bank holiday in some countries: https [...]
Please note that we do not consider extending again the deadline. The deadline for the submission of [...]
21/10/2019