1
|
According to your rules regarding people who are not considered a subcontractor (d) Use of staff without [...]
|
Thank you for your question. Please note that, as mentioned in the tender specifications under Criterion [...]
|
19/11/2020
|
|
2
|
Would you mind responding to the question regarding whether the three experts should be directly employed [...]
|
Question1
|
23/11/2020
|
|
3
|
Dear sir, madam, We would like to ask you to reconsider criterion T1. We have the impression that the [...]
|
Thank you for your question. Tenderers are requested to submit examples of past projects in the field [...]
|
24/11/2020
|
|
4
|
Dear DG EMPL, For criterion T1 on p.23 you state the following: "At least one project that included the [...]
|
Thank you for your question and for flagging this clerical error. As you rightly point out, the sentence [...]
|
24/11/2020
|
|
5
|
We would like to clarify if legal entities (private sector companies) registered in Switzerland will [...]
|
We refer to the Tender Specifications under chapter 2.2. ‘It is also open to all natural and legal persons [...]
|
24/11/2020
|
|
6
|
Dear Madam or Sir, on page 27 of the tender document the requirements of thte technical offers are described [...]
|
Thank you for your query. There is no limitation of length for the technical offers, although tenderers [...]
|
03/12/2020
|
|
7
|
Dear Madam, Sir, going forward with our offer we could not find a template document for the technical [...]
|
Thank you for the question. There is no template, nor format requirements for the technical offers, but [...]
|
07/12/2020
|
|
8
|
Dear sir, madam, Given the upcoming holiday period and Covid-related issues still persisting in many [...]
|
Thank you for your query. The deadline for submission has been established with taking into consideration [...]
|
09/12/2020
|
|
9
|
Dear Madam or Sir, we have a logistical question. Is it correct that the Declaration of Honour of each [...]
|
Thank you for your query. In case the tenderer (each partner of the consortium and the identified subcontractor [...]
|
17/12/2020
|
|
10
|
Dear Sir, Madam, regarding the Criterion F1, we kindly ask you to clarify the following point regarding [...]
|
Thank you for your question. We confirm that, in case of a joint tenderer, only those involved entities [...]
|
21/12/2020
|
|
11
|
Dear Mr/Madam; Regarding the Declaration on Honour (VII - Selection criteria), a question has arisen: [...]
|
Thank you for your question. In the case that you describe, the lead tenderer will tick YES under VII [...]
|
04/01/2021
|
|
12
|
The required evidence regarding criterion T2 is not quite clear to us. On p. 24, the requirement is described [...]
|
The detailed curriculum vitae of each staff member and expert responsible for carrying out the work must [...]
|
05/01/2021
|
|