2
|
• Do we need to offer all 43 as mandatory at phase 2? • Can we add subcontractors at phase 2 subject [...]
|
Please refer to the Answer to question 1.
|
06/06/2019
|
|
1
|
• Page 40 of the Tender Specifications asks for all 43 countries to be covered within 6 months but the [...]
|
All 43 countries need to be covered within six months following the contract’s entry into force (i.e. [...]
|
06/06/2019
|
|
3
|
Despite the initial declaration to be submitted according to the Annex 4, could DIGIT confirm that subcontracting [...]
|
Please refer to the Answer to question 1.
|
06/06/2019
|
|
4
|
since in the call for candidature foresees official declaration of co or sub-contractors requiring provision [...]
|
The contracting authority agrees to extend the deadline until 05 July 2019. A corrigendum to the contract [...]
|
06/06/2019
|
|
5
|
In the "invitation to Tender" there is, in the table on page 3, the relevant time to consider for the [...]
|
It refers to the end of the date mentioned, i.e., in your example, the midnight between June 21 and 22 [...]
|
06/06/2019
|
|
6
|
Must the contracts to fulfil the requirement be terminated before the 30.04.2019 or is it only relevant [...]
|
The contracts serving as reference may be ongoing, i.e. it is not a requirement that they have ended [...]
|
06/06/2019
|
|
7
|
In the case one of the tenderers satisfies a specific requirements by himself but should, during the [...]
|
As explained in answer to question 1, the contractor may sub-contract parts of the contractual execution [...]
|
06/06/2019
|
|
8
|
Is it possibile for a Tenderer leverage on the 27001 certification provided by a subcontractor that will [...]
|
The Contracting authority refers to the basis for assessment for criterion T5, as announced in the main [...]
|
06/06/2019
|
|
9
|
Statement no.1 by the contracting authority on the updated version of the Tender Specifications.
|
The contracting authority informs economic operators that an updated version of the “Tender Specifications [...]
|
06/06/2019
|
|
10
|
In regards to the PoP (Point of Presence) could you please clarify whether an actual presence (6 mandatory [...]
|
The Contracting authority confirms that an actual presence in 31 (of the 43) countries, of which 6 are [...]
|
11/06/2019
|
|