1
Is seems the financial offer form (annex 6) is missing. Could you please add it? Thank you very much
Annex 6 is not applicable for this procedure; a Corrigendum of the Administrative Annex has been published [...]
08/10/2020
2
With reference to the Tender Specifications (page 4, paragraph 1.5), the following sentence "The services [...]
The NUTS code indicated under Heading II.2.3 should indicate the main place of delivery or performance [...]
16/10/2020
3
Would you consider samples with less than 500 respondents in the medium-sized FUAs?
As indicated in the TENDER SPECIFICATIONS Part 2: Technical Specification, Chapter 4 Tasks, “Sample size [...]
20/10/2020
4
Due to the COVID-19 crisis, we are currently facing a new set of restrictive measures that would most [...]
The Contracting Authority considers that the current deadline for submission of offers gives ample time [...]
21/10/2020
5
Two questions regarding technical solvency (T1): -Are projects conducting large-scale surveys carried [...]
- Projects involving large-scale surveys of similar size and complexity (number of completed interviews [...]
21/10/2020
6
Podemos enviar ambas ofertas en español o tienen que ir en inglés. Gracias
Los idiomas en los que pueden presentar las ofertas se indican en el Capítulo IV.2.4) del Anuncio de [...]
23/10/2020
7
In the Call for Tenders, Technical Specifications, in Point 4 is specified: A draft questionnaire will [...]
The draft questionnaire provided by the Contracting Authority will not include any open ended question [...]
23/10/2020
8
Based on your answer to question #5, is the minimum requirement satisfied in the following circumstance [...]
As indicated in the TENDER SPECIFICATIONS Part 1: Administrative specifications, Chapter 3.2.3. Technical [...]
23/10/2020
9
The TS asks for 30 testing interviews in 3 cities. Does it mean 30 interviews PER city or 30 interviews [...]
The Pilot work must include 90 structured testing interviews in 3 cities (30 structured testing interviews [...]
23/10/2020
10
The list of tasks and related deliverables doesn't seem to include an analysis of data collected. The [...]
The Draft Final Report (D6) and Final Report (D7), must include a thorough description on the methodological [...]