Podrobnosti výzvy k podání nabídek

Název:
Observatoř obchodních inovací+.
Veřejný zadavatel:
European Innovation Council and Small and Medium-sized EnterprisesExecutive Agen...
Datum zveřejnění v TED:
17/06/2015
Lhůta pro podání nabídek:
19/08/2015
Stav:
Uzavřeno
Zobrazit parametry filtrů

Results per page: 10 | 25 | 50 11 Otázky found, displaying all Otázky .
# Otázka Odpověď Datum posledního zveřejnění Stav
2
Will these be one-day events, or should we allow for venue hire, catering and accommodation for two-day [...]
All the events will be one-day events
07/07/2015
1
On page 18 of the tender specifications, you summarise the videos to be produced by the contractor. Please [...]
No, the videos are not related to the events. As mentioned on p. 17 and p. 18 "The contractor shall produce [...]
07/07/2015
4
1. Regarding WP1 - Task 2, the first study to be delivered after 18 months, will extract barriers from [...]
As mentioned on p. 12 "In particular, the study shall: i. First, take into consideration the innovative [...]
10/07/2015
5
2. After step 1 (our previous question). The EU level overview of barriers produces in the first step [...]
As mentioned on p. 13: " The findings of this in-depth analysis based on the evidence gathered through [...]
10/07/2015
6
3. Based on our previous questions 2 and 3. Based on the previous steps a sample of MS is selected (6 [...]
While preparing the study "the contractor shall first look at the barriers existing at the EU level and [...]
10/07/2015
7
4. Following our previoous question 3. The barriers from the sample MS on national/regional level need [...]
As mentioned on p. 13: " The findings of this in-depth analysis based on the evidence gathered through [...]
10/07/2015
8
5. In regards with our previous questions 2 and 4. We should indicate or segment the results in actual [...]
Yes, that is correct. The findings of the study should be grouped and ranked.
10/07/2015
9
6. After the results coming from our previous questions 1 - 5. We should provide comperative insights [...]
As mentioned on p. 12, the contractor shall "examine in depth the obstacles that the selected innovations [...]
10/07/2015
10
7. Is it correct that all of the steps described in our previous questions 1-6 will be repeated for the [...]
The methodology and steps are the same for 2 studies. The first study shall concentrate on the case studies [...]
10/07/2015
3
8. If our previous questions are completely off mark. Could you please provide a bit more description [...]
As mentioned on p. 11-12: "The key objective of Task 2 is the preparation of a study on the regulatory [...]
10/07/2015
11
On p 18, it is indicated that 'The eLearning course shall be hosted on EASME's servers...'. However, [...]
No, there is no existing platform or Learning Management System. The tenderer has a freedom of proposing [...]
03/08/2015