1
|
'rules for pilot' mentioned on pg 12 paragraph 3.3 of the tender specifications document. Will this document [...]
|
Yes. Please Note the draft guidance documents referred to in the tender specifications have just been [...]
|
02/05/2013
|
|
5
|
- Is it correct that the work of the help desk relates exclusively to those pilot projects that will [...]
|
This is not correct. The work of the helpdesk will support all pilots selected (i.e. both those lead [...]
|
07/05/2013
|
|
4
|
The TS states that the contractor will gather and store all the “results” provided by the participants [...]
|
This requirement refers particularly to the inventory data provided under confidentiality agreement. [...]
|
07/05/2013
|
|
3
|
Which requirements are put on the review process and on the reviewer qualification? Is the formal review [...]
|
The previous reply could be misleading. What is meant is that the contractor will not have to systematically [...]
|
07/05/2013
|
|
2
|
Is it correct that it will not be the responsibility of the contractor to develop new data sets (e.g. [...]
|
It will not be the responsibility of the contractor to develop new data sets. It will be the responsibility [...]
|
07/05/2013
|
|
6
|
Can you please clarify what do you mean by “Among the different situations of exclusion, it is particularly [...]
|
NO, this clause is aimed at avoiding any evident conflict of interest which might cause a lack of trust [...]
|
08/05/2013
|
|
10
|
With regard to the criteria: "The tenderer must prove practical experience in the field of Life Cycle [...]
|
We ask for a "minimum" value if € 20.000 not for an "average" value of € 20.000.
|
16/05/2013
|
|
7
|
What kind of certificate would we need to provide as a Satisfactory Execution Certificate? Is it necessary [...]
|
There is no specific form or template for the certificate of Execution. This is usually in the form of [...]
|
15/05/2013
|
|
9
|
The tender refers to the development of e-learning packages. Could you confirm whether the contractor [...]
|
The tenderer/ contractor can choose any software for creating the e-learning package. Take into account [...]
|
16/05/2013
|
|
11
|
In case of public projects funded by European Commission (FP7, LEONARDO, SUDOE, etc.) it is necessary [...]
|
You are asked to provide a List of relevant services/projects giving details of sums, dates and recipients [...]
|
16/05/2013
|
|