Results per page: 10 | 25 | 50 9 Otázky found, displaying all Otázky .
# Otázka Odpověď Datum posledního zveřejnění Stav
1
Since there is a repetition in Criterion 1 and Criterion 2, we are in the need of clarifications. Do [...]
No. The tenderer must also demonstrate under Criterion A1 expertise in Communication in the field of [...]
03/07/2020
3
Can you confirm that following features added to Criterion A1 is not to be covered by 4 references because [...]
No. The tenderer must provide reference for four projects in all features described in Criterion A1, [...]
03/07/2020
2
Concerning Selection Criterion A(4), could you confirm that this criteria is related to the references [...]
No. The tenderer must prove its capacity to work in at least five EU Member States and the combination [...]
03/07/2020
4
Can you confirm that Drupal experiences, including for clients outside the European Commission, above [...]
Yes, the tenderer must provide reference for four projects delivered in all fields of Criteria A(1) in [...]
20/07/2020
5
In the criteria A for technical and professional capacity, project references are requested as a list [...]
Yes, the timeframe applicable is the one referred in each evidence required.
27/07/2020
8
Can completed phases of projects that are subject to renewal, that run under distinct contracts, and [...]
Yes, completed phases of project that are subject to renewal can be used as references.
29/07/2020
7
Can a project reference be used to fulfil multiple of the Criteria A for technical and professional capacity [...]
Yes, a project reference can be used to fulfil several of the Criteria A for technical and professional [...]
27/07/2020
6
On page 13 of the ToRs for task D the dissemination of a video is mentioned: “A press release, flash [...]
The contractor is not in charge of filming. The contractor will be provided with the video to upload [...]
27/07/2020
9
Should the time and resources allocated for overall reports, for the post-assessment report, for the [...]
The allocation of time and resources for each task or deliverable should be calculated separately.