2
|
The requirements for Criterion T1, related to tasks 3.1-3.4, and especially the required number of at [...]
|
This study is extensive and covers a wide range of aspects. The tenderer is required to prove sufficient [...]
|
28/05/2020
|
|
1
|
How does the contracting authority define experience in the field of "Union railway legislation"? Does [...]
|
Both types of experience mentioned in the question will be taken into account by the contracting authority [...]
|
28/05/2020
|
|
6
|
(3.1.1) Does the Commission expect analysis of ridership and supply data for every year from 2001 to [...]
|
The Commission expects an analysis of ridership and supply data for every year from 2001 to 2019. Where [...]
|
02/06/2020
|
|
8
|
(3.1.3, 3.1.5) Can the Commission provide further details of the study on high-speed rail and the matrix [...]
|
The study on high-speed rail will provide origin-destination matrices including distances and transit [...]
|
04/06/2020
|
|
5
|
(3.2.2) Can the Commission clarify which of the sub-tasks relate to all rail travel in EU+UK+NO+CH (as [...]
|
The subtasks described in task 3.2.2 should cover both of the below described geographical scopes: - [...]
|
02/06/2020
|
|
4
|
(3.2.2.9) Can the Commission provide details of any prior discussions with the Member States on the data [...]
|
So far, no discussion has taken place with Member States. Given the reporting deadline of 31/12/2022, [...]
|
02/06/2020
|
|
3
|
Can the Commission indicate when the next RMMS is expected to be published?
|
Publication of the next RMMS is expected tentatively around December 2020.
|
02/06/2020
|
|
7
|
Does DG MOVE expect a full coverage of international passenger travel in the study? Or should activities [...]
|
Last section of paragraph 2.1 of the technical specifications of this tender states as follows: “The [...]
|
04/06/2020
|
|
12
|
Are bidders expected to fully cost venue and catering for the conference in the bid or can this element [...]
|
Bidders should cost venue and catering for the conference in the bid. The payment arrangements are presented [...]
|
09/06/2020
|
|
10
|
Given the payment criteria are subjective (on quality rather than delivery) can the Commission provide [...]
|
Section 6 of the Technical Specifications provides guidance on the drafting of reports.
|
08/06/2020
|
|