2
|
Can you please clarify whether the energy range required for the HpGe detectors (see page 7/15 of the [...]
|
Even if the probability of detecting 3 keV gamma rays could be low, considering that the detector will [...]
|
07/11/2017
|
|
1
|
Can you please state the maximum expected density of the material to be characterised?
|
The real density of the single piece of the objects to be measured can be up to 20 g/cm3 while the density [...]
|
07/11/2017
|
|
3
|
please inform if the ESTIMATED TOTAL VALUE of each lot can be exceeded?
|
The Tender specifications: Part 1- Administrative Annex states in point 2.4 that tenders may be considered [...]
|
08/11/2017
|
|
4
|
What shall we interpret the following statement? "Each detector shall be connected to...PMT bases with [...]
|
Each module of the VETO System includes a plastic scintillator, PMT and PMT base and shall have one connector [...]
|
09/11/2017
|
|
5
|
System we will propose is compliant with all tech. specifications ( many of them are superior than the [...]
|
Please note that the technical specifications "Acquisition of radiometric equipment - Supply and installation [...]
|
10/11/2017
|
|
6
|
Can you please confirm that the size of the whole structure (75 x 58 x 76 cm +- 5%) is inclusive of cart [...]
|
Yes, we confirm that the dimensions of the instrument specified in the technical specifications includes [...]
|
16/11/2017
|
|
7
|
Question to LOT 7: In supply description (chapter 5) is stated „The size of the whole structure (instrument [...]
|
The full size (including any accessories or tools) of the instrument is fixed due to the space constraints [...]
|
22/11/2017
|
|
8
|
Is it expected that only plastic detectors with PMT Bases+BNC cables should be delivered and installation [...]
|
See § 6.1.0.1 c) of the technical specification: "The supply of the detection system consists of (c) [...]
|
28/11/2017
|
|
9
|
Please provide required length of BNC cables.
|
The minimum distance between the VETO detectors and the IDAS (Integrated Digital Analysis System – see [...]
|
28/11/2017
|
|
11
|
If I want to submit the tender not as solo but with a group (joint tender, subcontractors or third party [...]
|
For each selection criterion, whether financial (section 2.3.2 of the administrative annex) or technical [...]
|
29/11/2017
|
|