23
|
In order to submit a high quality response, can we request an extension of the deadline by 15 days to [...]
|
Please note that we do not consider extending the deadline. The deadline for the submission of tenders [...]
|
11/10/2019
|
|
29
|
Can you please confirm that we can cross-reference between questions in our reply in the technical tender [...]
|
There is no specific requirement regarding the format of the reply, as long as "The Technical proposal [...]
|
14/10/2019
|
|
30
|
In Question 19 you state that 'prices tendered for shall include all the costs to be incurred by the [...]
|
(a) Technical infrastructure means hardware and software needed for developments in Proximity and Near [...]
|
14/10/2019
|
|
31
|
You mention that "KPI-1: Failure to provide a suitable proposal activates the payment of a compensation [...]
|
KPI-1 applies also where there is no answer to the request. The different cases of failure to make a [...]
|
14/10/2019
|
|
21
|
We need some clarifications regarding a profile: Portfolio Manager (POM) - Can you please confirm that [...]
|
Portfolio Manager (POM) will manage the portfolio of all EEAS projects related to the EEAS Information [...]
|
11/10/2019
|
|
22
|
We need some clarifications regarding a profile: Will the Technical Team Leaders (TTL) be of the Project [...]
|
As indicated in 2.7. Technical Teams and Project teams of the Technical Specifications "One of the profiles [...]
|
11/10/2019
|
|
32
|
In Part II technical specifications, point 2.4 Place of Delivery there it is mentioned that for Proximity [...]
|
(a) and (b): As stated in the Tender Specifications (6.3. Financial Tender), "the prices are all inclusive [...]
|
15/10/2019
|
|
33
|
With reference to the documents which need to be provided in case of subcontracting, our understanding [...]
|
a) Yes, we confirm your understanding. As indicated in the tender specifications point 4, "Tenderers [...]
|
15/10/2019
|
|
34
|
It is our understading that the description of the tender is not included in the page limit of 80 pages [...]
|
The description of the tender will be counted within the 80-page limit. Regarding the 80-page limit, [...]
|
17/10/2019
|
|
35
|
Is the EEAS expecting a full Service Management Quality Plan (SMQP) in this answer? Or is the EEAS only [...]
|
The description of your proposal of SMQP does not need to be long, but should provide enough information [...]
|
17/10/2019
|
|
37
|
In the e-Submission platform, in the Tender offer step, the following fields are mandatory: Total amount [...]
|
As indicated in the e-Submission Quick guide in tender specifications point 3, you must fill in the total [...]
|
17/10/2019
|
|
36
|
In the invitation to tender we read: The hand-signed originals (Tender report and Declaration on Honour [...]
|
Yes, we confirm that the hand-signed originals must be sent to the European External Action Service, [...]
|
17/10/2019
|
|
39
|
Procurement documents state: "The Contractor shall propose per requested profile at least 2 and maximum [...]
|
As stated in 4.2.1 Request, "QTM requests contain a Technical Annex detailing the different tasks to [...]
|
17/10/2019
|
|
40
|
In technical tender award sub-criterion 2.1 you mention "processes, interfaces, responsibilities, structure [...]
|
Processes is a generic term referring here to the manner in which the work/activities/information/knowledge [...]
|
17/10/2019
|
|
41
|
Our understanding is that we can submit answer to the 4 blocks of the technical questions in separate [...]
|
We do not confirm your understanding. As stated in 14. Annex 2 – Technical tender, “The tenderer will [...]
|
17/10/2019
|
|
44
|
Our understanding is that the cover, table of contents and question description are not counted in the [...]
|
The cover and table of contents are not counted in the limit of 80 pages.
|
17/10/2019
|
|
42
|
You state in terms of Contractor's entities the following:(Account Manager, Contract Manager, Service [...]
|
Indeed, in Technical specifications, point 7.2. Steering Committee meetings, it is mentioned "The Steering [...]
|
17/10/2019
|
|
43
|
Since we need to respect the 80 pages limitation, is it possible to put in annex all graphs and images [...]
|
All graphs, images (including organigrammes) will be counted within the 80-page limit.
|
17/10/2019
|
|
38
|
According to Q&A #33, our understanding is that in case tenderers aim to bring a subcontractor whose [...]
|
As stated in point 4.2 of tender specifications "Tenderers must give an indication of the tasks that [...]
|
17/10/2019
|
|
45
|
In reference to Q&A 2, can you please confirm that the illustrative example of Q.3.2 can also be [...]
|
We expect practical examples illustrating tenderers' answer. These examples do not need to be complete [...]
|
17/10/2019
|
|
48
|
Can we please request an extension of the submission deadline by 1 week?
|
Please note that we do not consider extending the deadline. The deadline for the submission of tenders [...]
|
18/10/2019
|
|
49
|
When requesting to specify the structure of QTM proposals, do you mean to provide a template or something [...]
|
Structure refers here to a general description or plan showing the essential features of your answer. [...]
|
21/10/2019
|
|
46
|
Since customers in the public sector in some EU Countries tend not to sign statements, could it be acceptable [...]
|
As indicated in tender specifications point 5.3.3 a) "For each contract in the table (list), the tenderer [...]
|
17/10/2019
|
|
47
|
Would you accept a declaration from the auditor, since the national law does not provide for the obligation [...]
|
Please note that the client's reference letters requested under point 5.3.3. a) of the tender specifications [...]
|
18/10/2019
|
|
50
|
In relation to the page limitation - 80 pages, is it allowed to have some graphs in the 80 pages at reduced [...]
|
All graphs will be counted within the 80-page limit. However, we accept that some graphs at reduced size [...]
|
21/10/2019
|
|