50
Under other Framework contracts, we already provided QTM services from our premises. Would that be possible [...]
Yes, QT&M assignments may be performed in the contractor’s premises in case such a place of performance [...]
23/05/2016
51
While item 100 is entitled "Training for end users", its description reads "Training shall effectively [...]
Yes, this a typo in the requirement. Item number 100 addresses training of End Users.
24/05/2016
52
In the invitation letter, it states: "Requests for additional information received less than six working [...]
The deadline for submitting questions and/or requests for additional information is Monday, 30th May [...]
24/05/2016
53
The description reads "For each offered persons there shall be attached the following documents: CV, [...]
The requirement to submit the Statement of Intent applies for each individual included in the proposal [...]
24/05/2016
54
The questions we have refers to one of the selection criteria - III.4.3 Technical and professional capacity [...]
1. Confirmed references shall be understood as reference letters issued and signed by the Clients (copies [...]
24/05/2016
57
We would like to ask you for more details on Agency´s possible ROAD MAP of future requirements for different [...]
The TOR provides concise yet comprehensive description of the current status of SP based developments [...]
01/06/2016
58
Can you give us your estimate on possible place of performance: what share could be accounted for intramural [...]
It can be assumed that majority of the assignments will be “intramural”. “Other locations” are practically [...]
01/06/2016
59
Some of COTS or 3rdP software we are going to put on Price List usually needs some maintenance and insurance [...]
The tenderers are requested to submit their Official Price List in the form of the table presented in [...]
01/06/2016
62
Due to the large number of received questions and answers as well as the requirements regarding of the [...]
The deadline shall not be postponed. None of the questions and replies has lead to the alteration of [...]
01/06/2016
55
Can the offer be prepared in Polish language?
Preferably the offer shall be submitted in English. Polish, as well as other official languages of the [...]
25/05/2016
72
Could you please provide us with a rough estimate of the share between Fixed Price, Time-and-Means, and [...]
At this stage Frontex cannot declare the volume and proportions of the different types of assignments [...]
02/06/2016
63
Are we allowed to provide more than three references? And if we are, do all of them have to be confirmed [...]
Yes, more then three references may be provided. At least three of the references must meet the conditions [...]
01/06/2016
67
In Terms of Reference, p. 42, paragraph 10.2. reads: ''The required statements based on the templates [...]
The copies of the personal certificates shall be included in the offer. They can be either included in [...]
01/06/2016
73
Point 7.4 in Annex II states: "The guarantee for the Products acquired via this FWC is for minimum 2 [...]
As indicated in the citations, the price of 2 years guarantee shall be included in the purchase price [...]
02/06/2016
60
Does the Article II.8 relates also to subcontractors and members of consortium?
Yes.
01/06/2016
68
Do you agree on changing the duration of confidentiality obligations from Article II.8 for 5 years after [...]
There's no particular period specified. The nature of confidentiality of particular information or documents [...]
01/06/2016
61
Do you agree on adding point (d): “for the contractor: the contractor discloses confidential information [...]
Frontex shall not agree to the introduction of the proposed article.
01/06/2016
69
Does “any outside body authorised to do so on its behalf” from Article II.24.1 is an EU body or independent [...]
The reference is made to the situation when the task may be assigned by OLAF to another entity (e.g. [...]
01/06/2016
66
Do you agree on limiting audits to one per year?
Frontex cannot accept such limitation, although it is highly unlikely that the implementation of the [...]
01/06/2016
64
Do you agree on reconciling principles of an audit with the contractor before initiating an audit?
In case the audit shall be initiated by Frontex some principles shall be reconciled beforehand with the [...]
01/06/2016
71
Is there a possibility for SC to provide implementation services by one vendor and 3rd Level Support [...]
Such a situation is potentially possible, especially when it comes to maintenance of legacy system. By [...]
02/06/2016
70
What are the Frontex Security Rules that Contractor should respect with each Specific Contract? What [...]
In general, the security rules concern the access to Frontex premises, documents and systems. As indicated [...]
02/06/2016
65
In case of further inaccuracies/questions/doubts found, do Frontex consider postponing the deadline?
The deadline shall not be postponed. None of the questions and replies has lead to the alteration of [...]
01/06/2016