1
|
As per Technical Specifications it is stated that the Lots will be awarded with re-opening of competition [...]
|
The European commission is launching an open call for tenders with three lots. The two first lots will [...]
|
24/06/2019
|
|
2
|
We have noticed that the number of years of experience requested for the Senior Consultant Profile in [...]
|
The subjects of each Lot differ; therefore, different selection criteria are required and so, we confirm [...]
|
28/06/2019
|
|
3
|
In the "Selection Criteria" for LOTs 1, 2 and 3 (pages 25,27 and 28) it is stated in "Resources" that [...]
|
The goal of this selection criteria is that a company who wants to participate in different lots can [...]
|
09/07/2019
|
|
4
|
Dear, Since, in the 'Technical and Professional Capacity' section, there is no minimum number of projects [...]
|
The list to be provided should contain all services provided in the past three years in the field of [...]
|
10/07/2019
|
|
5
|
Referencing your answer n. 4 answered on 10/07/2019, is it enough to present one project which amounts [...]
|
There is no minimum number of projects to be listed under the Technical and professional capacity selection [...]
|
24/07/2019
|
|
6
|
In Section 6.8 ‘Scenarios’, page 55, in the last paragraph there is a reference to ‘tables as contained [...]
|
The financial proposal has to be submitted by filling out the table in Annex 6.9. This annex is provided [...]
|
18/07/2019
|
|
7
|
In Section 5.3 ‘Application of award criteria (assessment of tenders)’, page 33, are ‘Points n’ based [...]
|
The application of Award criteria, resulting in scoring points, is based on assessment of the respective [...]
|
23/07/2019
|
|
8
|
In Section 5.2.1 of the Tender Specifications document, for Lot 1, Subsection 2.3, the selection criteria [...]
|
The three Senior Consultants for Lot 1 must fulfil minimum years of experience in both areas mentioned [...]
|
23/07/2019
|
|
9
|
Looking at the task mentioned in Section 1.1.1, we have difficulties understanding what the Graphical [...]
|
All tasks and specific contracts placed under this framework contract will have deliverables. Some of [...]
|
23/07/2019
|
|
10
|
Referring to the tender in object, we would like to ask you a clarification on the references: activities [...]
|
Could you please develop the question in more detail including, referring to a page or chapter of the [...]
|
23/07/2019
|
|