Podrobnosti výzvy k podání nabídek

Název:
Poskytnutí služeb družicových komunikačních systémů (SATCOM) pro systém dálkově ...
Veřejný zadavatel:
European Maritime Safety Agency
Datum zveřejnění v TED:
31/03/2018
Lhůta pro podání nabídek:
21/05/2018
Stav:
Uzavřeno
Zobrazit parametry filtrů

Results per page: 10 | 25 | 50 45 Otázky found, displaying 1 to 25.[First/Prev] 1, 2 [Next/Last]
# Otázka Odpověď Datum posledního zveřejnění Stav
1
Dear Sir/Madam, With regard tot he terminals that will need to go onto the 2 different types of RPAS. [...]
1. The details of the first type of RPAS are: TAKE-OFF WEIGHT / MASS UP TO 150 KG (MAXIMUM) ENDURANCE [...]
11/04/2018
2
Dear Sir/Madam, Can we request an area of operation that the RPAS will require to have BLOS communications [...]
The areas of operation can be all sea areas surrounding the European Union with an EU or EFTA country [...]
11/04/2018
3
With reference to Paragraphs 2.2.2 & 2.2.3 & 8.1.2 in the Tender Specification document (EN-02 [...]
The Contracting Authority may award several FWCs per lot. The mechanism for implementing the FWC per [...]
20/04/2018
4
With reference to the second bullet point in paragraph 8.1.2 in the Tender Specification document (EN [...]
During the implementation of the FWC, the Contractors may add new terminals in order to ensure SATCOM [...]
20/04/2018
5
Can the same company be subcontractor in more than one tender to the FWC?
Please refer to point 10 of the Tender Specifications - economic operators on the market are free to [...]
20/04/2018
6
To provide an offer in Mbps, it is required to establish a link budget. Can you provide details about [...]
The details of the terminals currently used by the Agency can not be provided. The terminal requirements [...]
20/04/2018
7
Can you confirm: - The method used to evaluate the link availability (exclusions, periods of time to [...]
-The Bidders can select the method that they consider more suitable to evaluate the link availability [...]
20/04/2018
8
Are there alreary routers, and of which type, aboard the current fleet of RPAS ? Will it be the responsibility [...]
The Agency operates with different RPAS platforms, most of them already have routers on-board to distribute [...]
20/04/2018
9
As some French overseas territories are included in the EU territory according to international treaties [...]
As per Tender Specifications: 1.1.8 and Appendix 1: 2.1: Areas of operation can be all sea areas surrounding [...]
20/04/2018
10
a) Will EMSA please verify the SATCOM equipment the vendors propose for Lot 1, (2 Mbps data rate) is [...]
a) In principle both lots are intended for fixed wing RPAS. The Agency's current platforms are medium [...]
20/04/2018
11
Concerning point 15.4: what are the criteria adopted for assessing the financial capacity? What is the [...]
The basic method is the analysis of the tenderer’s annual accounts (or financial statements). The financial [...]
23/04/2018
12
Concerning Appendix 1 point 2.4.: How many SATCOM terminals have to be provided for each size (medium [...]
There is no minimum nor maximum number of terminals that must be offered per category. Offers will be [...]
23/04/2018
13
With reference to EN-03 Tender Specifications Appendix 1 Technical Specifications.pdf section 2.1.1, [...]
The latency requirement of 2s shall be maintained at least between the RPAS and the LGCS. The Agency [...]
23/04/2018
14
With reference to EN-03 Tender Specifications Appendix 1 Technical Specifications.pdf section 2.1.1, [...]
It is the Bidders choice to use the same SATCOM terminal for the primary and the secondary Command and [...]
23/04/2018
15
Is it possible to make an inspection on site for a better understanding of installation, configuration [...]
An on-site inspection is not available during the tender process. Note that the sites themselves are [...]
23/04/2018
16
With reference to EN-03 Tender Specifications Appendix 1 Technical Specifications.pdf section 2.1.1, [...]
Yes, the Command and Control link data rate applies to both the return and forward link. The data rate [...]
23/04/2018
17
With reference to EN-03 Tender Specifications Appendix 1 Technical Specifications.pdf section 2.5.1, [...]
The required throughput is symmetric 10Mbps as defined in point 2.5 of Appendix 1 Technical Specifications [...]
23/04/2018
18
Dear sir/madam, due to the complexity of this project, we kindly request the extension of the deadline [...]
EMSA understands the complexity of the tender and for that reason already foresaw a bid submission period [...]
23/04/2018
19
1. Do you already have aircrafts or UAVs in operation or should they will be offered here as well? 2. [...]
1. EMSA already has RPAS in operation as well as a new procurement for large size RPAS (EMSA/OP/1/2018 [...]
23/04/2018
20
§1.1.1: How many RPAS are or will be deployed at the same time at most? Could you please give us an estimation [...]
The RPAS services are offered by EMSA free of charge to EU Member States, Candidate Countries and EFTA [...]
30/04/2018
21
§1.1.2: Could you please indicate the customer POP where all the traffic should be delivered?
The POP where all the traffic should be delivered will be the Local Ground Control Station (LGCS) that [...]
30/04/2018
22
§1.2.4: Could you please provide the delivery point for the VSAT equipment? To EMSA premise? Or at the [...]
The delivery point for the VSAT equipment will be the place of the RPAS mission location as indicated [...]
30/04/2018
23
§2.4: Will the customer have a router integrated in each RPAS? If yes, could you please specify the brand [...]
EMSA operates with different RPAS platforms,those meant to be operated beyond Radio line of Sight already [...]
30/04/2018
24
§6.1.2: Where will take place the integration of SATCOM antenna on the RPAS?
The installation of the SATCOM terminal on the RPAS is an activity that shall be covered by the terminal [...]
30/04/2018
25
§1.1.8: Could you please confirm that the teleports must be located in an EU country for security reason [...]
In the Tender Specifications there are no requirements on the location, the level of accreditation and [...]
30/04/2018