1
The profile "System Administrator" appears in the Profile Listing but does not appear in the financial [...]
The inclusion of the “System Administrator” profile in “2.4.6 Service delivery team and profiles” (and [...]
15/06/2018
Beantwortet
2
Could you please specify how the CVs should demonstrate those requirements addressed as "good understanding [...]
The evaluation committee will consider both practical experience and training as sufficient evidence [...]
18/06/2018
Beantwortet
3
Profile "System Developer" addresses 10 different "technology and eco-system" areas. We understand it [...]
Correct. CVs submitted for “3.2.3 Technical and professional capacity” and the “System Developer” profile [...]
18/06/2018
Beantwortet
4
We understand that the addressed number for each profile (e.g. 1 x Account Manager) means the minimum [...]
The numbers of CVs expected described in “3.2.3 Technical and professional capacity” for the “Team profiles [...]
18/06/2018
Beantwortet
5
According to the Tender Specifications page 63: "In case of a consortium, the tender must include three [...]
In regards to “3.2.3 Technical and professional capacity”, the sentence (on page 63) “In case of a consortium [...]
19/06/2018
Beantwortet
6
If the answer to the previous question is yes, we understand that, for complying with the technical selection [...]
In regards to “3.2.3 Technical and professional capacity”, and the “Team profiles” and the profile “2 [...]
19/06/2018
Beantwortet
7
In cell I43 od sheet "Financial Scenario" of the Financial proposal form, the extramural effort (cell [...]
Indeed a clerical mistake. An corrigendum of Annex II (Financial proposal) will be published shortly.
19/06/2018
Beantwortet
8
We interpret 2.9.2 Estimation methodology to be agreed upon as part of the kick-off meeting hence not [...]
As stated in “4.1 Technical proposal”, the estimation methodology must be included in the “Service Delivery [...]
19/06/2018
Beantwortet
9
Our understanding is that we can use our own template to submit the references. Could you please confirm [...]
Any template can be used for the references requested in “3.2.3 Technical and professional capacity” [...]
19/06/2018
Beantwortet
10
Would it be possible for ECDC to prolong the tender period considering the amount of work needed to respond [...]
Considering that there is still a full month remaining until the deadline, we do not see an extension [...]