Предмет
Work Package 2 - Updating of databases Task 2.8: Management and further development of KETs Observatory, mapping of KETs Technology Centres and DTM web tools
Въпрос
Page 19 of terms of reference states that contractor should provide content developed in WP1 to 3, including datasets of indicators developed and continuously updated. Could you please specify and detail which are the indicators to be "continuously" updated on the web to not enter into conflict with previous regular updates foreseen in the indicative planning?
Отговор
18/04/2018
The indicators which are referred to under Task 2.8 shall be indeed regularly updated according to the indicative planning. The updated indicators shall be published on the website.