Θέμα
Meeting of experts p.25 of the Tender Specifications
Ερώτημα
Page 25 of the Tender Specifications states: "The contractor shall after 9 months provide a second interim report to: - a meeting of private experts (quality assessment) - a meeting of national experts on national procedures in the field" What is meant by "private" experts, and is it intended that these meetings are separate?
Απάντηση
19/08/2015
As indicated under point 8 in the technical specifications, the contractor may be required to attend a meeting to present and discuss the second interim report with the groups of experts. It would therefore be sufficient to hold a single meeting with the groups of expert referred to under point 7 to discuss the second interim report.