Call for tenders' details
Status
Submission date
12/07/2018
Answer date
12/07/2018
Language
Status
Answered
Question details
Subject
Page 5: Kick-Off Meeting ( 1 day at Frontex Headquaters)
Question
Is it right, that we should present the corresponding elaborated delivieries with our Team at Frontex?
Answer
12/07/2018
Kick-off meeting (1 day at Frontex Headquarters) a. Introduction to Frontex b. Sharing documents for scenario preparations c. File sharing platform (share point based) to be used d. Prepare minutes of the meeting by contractor The meeting serves as the first introductory contact between the contractor and Frontex. No presentation of elaborated deliverables of the contractor are expected at this meeting. That will be subject of further communication at later stage, in the process of preparation and/or execution of the deliverables.