Subject
Special surveys' costs
Question
According to p. 13 of the ToR: "Special surveys such as topographic, geological, geotechnical, environmental, climate assessment, purchase of maps etc. as required by each sub-project are subject to prior written approval by the Contracting Authority, and should be provisioned for and the related costs included in the price. The selection of projects should be made with consideration to the budget available for surveys, in light of that no additional budget is available for this." Does this imply that such costs are included in the Global price for this contract?
Answer
04/11/2019
The contracting Authority confirms that all costs for special surveys are to be included in the Global price for this contract.