Supply, installation and maintenance of 2 battery storage systems - 2 lots.
Contracting authority:
European Commission, Joint Research Centre (JRC)
TED publication date:
31/07/2015
Time limit for receipt of tenders:
28/09/2015
Status:
Closed
Status
02/09/2015
03/09/2015
English (en) italiano (it)
Question details
Annex 1 Lot 1 and 2 Key technical requirement B3 e B4
Are continuous Power and Peak Power refer to AC (at the connection point with the network) or DC? Are these powers of reference for both the discharging phases and those of charging?
03/09/2015
B3 and B4 refer to AC power (at the connection point with the network) for both charging and discharging phases.