Section 2.2.2.3. Organisational support Tool for presenting activities of the Digital Skills and Jobs Coalition - the contractor will maintain the website and database of the Pledgeviewer.
Küsimus
Please clarify, how the contractor is expected to manage Pledge viewer website content: is the contractor expected to add and update all content, or to review and upload content provided by pledgers? Is the contractor expected and allowed to add new features to the website (requires full access to website code, programming new features), or maintain existing functionalities?
Vastus
10/12/2018
In accordance with the Invitation to Tender, Section 3.1, The contracting authority is not bound to reply to requests for additional information received less than six working days before the time-limit for receipt of tenders. Please see also
Question4