Kysymys
• The Annex V: Budget defines five interim payments, which make the total amount of the financial proposal. However, article 6.7 Lump Sums of the TOR indicates “No lump sums are foreseen in this contract”. How should we understand article 6.7? • The Annex V: Budget does not show an advance payment for the Consultant. Can you specify if an advance payment will granted to the Consultant?
Vastaus
04/11/2019
The contractual payment conditions are described in Article 7 of the Special Conditions of the Service Contract. No Lump Sums payments are foreseen. Payments are subject to approval of the deliverables as described in Article 7.2 of the Special Conditions of the Service Contract. An advance payment of up to 30% of the maximum contract value is foreseen.