Detalji pitanja
Related to TS, Page 21, Duration of the tasks
The project tasks 1 and 2 need to be completed in 24 months. In a logical sequence, six sites that need support would be identified after inventarisation and risk ranking/prioritization of all sites, However based on the time available it is our understanding that Task 1 and 2 need to be executed in parallel. Is it correct to assume that the list of six projects selected for phase 2 will not be adapted based on the outcome of Task 1, but is defined only in the project preparation phase?
16/09/2019
Indeed, the duration of the contract of 24 months will probably require parallel and independent execution of tasks 1 and 2. The projects/cases will not be adapted based on the outcome of task 1 and have to be defined in the offer.