Id-Dettalji tas-Sejħa għall-Offerti

It-titlu:
European Training Programme in Entrepreneurship for Educators
L-Awtorità li Qiegħda Toħroġ il-Kuntratt:
European Innovation Council and Small and Medium-sized EnterprisesExecutive Agen...
Id-data tal-pubblikazzjoni tat-TED:
17/08/2018
Limitu ta' żmien għall-wasla tal-offerti:
15/01/2019
L-istatus:
Magħluq
L-istatus
10/01/2019
11/01/2019
English (en)
Id-Dettalji tal-Mistoqsija
EN-Annex 2-Letter of submission of tender - Subcontractors
The footnote on Page 2 of 3 of Annex 2 section 1.4 'Sub-contractor's details states: "This section must be completed for each sub-contractor whose share of the contract is above 30%" This would imply this section is not to be completed for identified sub-contractors whose share of the contract is below 30%, even whilst they are identified. Can you confirm that this is correct?
11/01/2019
Yes, the section 1.4 in annex 2 must be completed only for the sub-contractors whose share of the contract is above 30%.