Szczegóły ogłoszenia o przetargu
Status
Data przesłania
15/03/2017
Data odpowiedzi
20/03/2017
Język
Status
Udzielona odpowiedź
Szczegóły pytania
Temat
Par. 5.1.3. "Hand-over"
Pytanie
According to section “5.1.3 Hand-over” of the Questionnaire, the contractor is called to show its plan on how it proposes to ensure the hand-over of existing QA3 services while ensuring the running of its services. Meanwhile, according to WP.5 of “Annex 2b: Technical Annex”, the hand-over activities relate to QA4 services. Please clarify that section 5.1.3 of the Questionnaire refers to hand-over of future QA4 services to the next contractor.
Odpowiedź
20/03/2017
We do confirm a clerical mistake. Section “5.1.3 Hand-over” of the Questionnaire should read: "Its proposed strategy for the hand-over (WP.5), its plan (planning, work breakdown structure, deliverables, external and internal dependencies, milestones, critical path, tools…) showing how it proposes to ensure the hand-over of existing QA4 services while ensuring the running of its services." An updated Questionnaire is published on the eTendering platform.